5863 W 1ST ST 90036
Certificate Information: 5863 W 1ST ST 90036
- Application / Permit
- 23010-20000-04619
- Plan Check / Job No.
- B23VN15829
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERSION OF (E) GARAGE TO NEW 17'-4" x 26'-7" TWO-STORY DET. ACCESSORY DWELLING UNIT [PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)]
- Permit Issued
- Issued on 2/29/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2023 | SEAN SHAHMIRI |
| Corrections Issued | 12/7/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 12/7/2023 | STEVEN KIM |
| Building Plans Picked Up | 12/12/2023 | APPLICANT |
| Applicant returned to address corrections | 1/25/2024 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 1/31/2024 | SEAN SHAHMIRI |
| Plan Check Approved | 2/29/2024 | SEAN SHAHMIRI |
| Issued | 2/29/2024 | APPLICANT |
| CofO in Progress | 5/7/2026 | JOSH MEISTER |
| Permit Finaled | 5/8/2026 | DEROLD HAUFF |
| CofO Issued | 5/8/2026 | DEROLD HAUFF |
| Permit Finaled | 5/8/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/19/2023 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 12/21/2023 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 12/22/2023 | JUSTIN BICOL |
| HPOZ | Cleared | 1/9/2024 | DAMIAN GATTO |
| ZI | Cleared | 1/9/2024 | DAMIAN GATTO |
| Construction near power lines | Cleared | 1/12/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 1/12/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | David Elliot Builders Inc; Lic. No.: 1021000-B | 5979 W 3RD ST SUITE #203 LOS ANGELES, CA 90036 |
| Engineer | Mercado,, Lizandro; Lic. No.: S4331 | 27240 TURNBERRY LN STE 200 VALENCIA, CA 91355 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/7/2024 | Approved | AMIR NAZARIAN |
| Footing/Foundation/Slab | 6/14/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Barrier | 6/14/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Subgrade | 6/14/2024 | Corrections Issued | AMIR NAZARIAN |
| Sewer | 6/24/2024 | Approved | AMIR NAZARIAN |
| Underground Mechanical | 6/24/2024 | Approved | AMIR NAZARIAN |
| Footing/Foundation/Slab | 8/14/2024 | Approved | AMIR NAZARIAN |
| METHANE-Barrier | 8/14/2024 | Approved | AMIR NAZARIAN |
| METHANE-Subgrade | 8/14/2024 | Approved | AMIR NAZARIAN |
| Deputy Reinf. Concrete | 8/15/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Rough | 11/18/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2024 | Conditional Approval | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 1/21/2025 | Approved | JOSE MACIAS |
| HVAC-Rough | 1/21/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 1/21/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 2/14/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 2/14/2025 | Approved | JOSE MACIAS |
| METHANE-Rough | 2/14/2025 | Approved | JOSE MACIAS |
| Shower Pan | 2/14/2025 | Approved | JOSE MACIAS |
| Insulation | 3/14/2025 | Approved | JOSE MACIAS |
| Drywall Nailing | 3/24/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 5/15/2025 | Approved | ALEX COLIN |
| Special/Order Compliance | 1/14/2026 | Corrections Issued | JOSH MEISTER |
| Gas Test | 3/19/2026 | Approved | JOSH MEISTER |
| PLUMBING-Final | 3/19/2026 | Corrections Issued | JOSH MEISTER |
| HVAC-Final | 4/17/2026 | Approved | JOSH MEISTER |
| PLUMBING-Final | 4/17/2026 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 5/4/2026 | Corrections Issued | JOSH MEISTER |
| ELECTRICAL-Final | 5/6/2026 | Approved | JOSH MEISTER |
| Final | 5/6/2026 | OK to Issue CofO | JOSH MEISTER |
| Green Building Final | 5/6/2026 | Approved | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 5/6/2026 | SGSOV Approved | JOSH MEISTER |
| Service/Power Release | 5/6/2026 | Approved | JOSH MEISTER |
| Smoke Detectors | 5/6/2026 | Approved | JOSH MEISTER |