10375 N RINCON AVE 91331
Certificate Information: 10375 N RINCON AVE 91331
- Application / Permit
- 23010-20000-04579
- Plan Check / Job No.
- B23VN15705
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached 2 Story ADU in the rear yard "COMPLY WITH DEPARTMENT ORDER effective date 01/18/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
- Permit Issued
- Issued on 7/29/2024
- Issuing Office
- Current Status
- Issued on 7/29/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2023 | SUNMIN LEE |
| Corrections Issued | 12/11/2023 | SUNMIN LEE |
| Quality Review Completed | 12/14/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 1/25/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 6/6/2024 | SUNMIN LEE |
| Plan Check Approved | 6/13/2024 | SUNMIN LEE |
| Issued | 7/29/2024 | APPLICANT |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 12/18/2023 | STEVEN WECHSLER |
| ZI | Cleared | 12/18/2023 | STEVEN WECHSLER |
| Address approval | Cleared | 1/4/2024 | RYAN KIM |
| Construction near power lines | Cleared | 1/4/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2024 | RYAN KIM |
| Sewer availability | Cleared | 1/4/2024 | RYAN KIM |
| Roof/Waste drainage to street | Cleared | 5/30/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/14/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2025 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2025 | Corrections Issued | KEVIN BERBERYAN |
| Deputy Wood Construction | 11/10/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/12/2025 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 11/12/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 11/12/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/12/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Sewer | 11/12/2025 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 11/12/2025 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 11/12/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/5/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/5/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2025 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 12/5/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/5/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/11/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/18/2025 | Approved | MICHAEL CORTEZ |
| Insulation | 12/30/2025 | Corrections Issued | LOUIS ESCOTO |
| Special/Order Compliance | 12/30/2025 | Corrections Issued | LOUIS ESCOTO |
| Insulation | 1/15/2026 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 1/23/2026 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/23/2026 | Approved | MICHEL ABAJAN |
| Shower Pan | 1/23/2026 | Approved | MICHEL ABAJAN |