12183 W KESWICK ST 91605
Certificate Information: 12183 W KESWICK ST 91605
- Application / Permit
- 23010-20000-04561
- Plan Check / Job No.
- B23VN15642
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 20'0"X24'11" SB9 UNIT PER WFPP. NFPA 13 D FIRE SPRINKLERS REQUIRED THROUGHOUT. [ALL ELECTRIC BUILDING]
- Permit Issued
- Issued on 5/29/2024
- Issuing Office
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2023 | MARVEL DELACRUZ |
| Corrections Issued | 12/5/2023 | MARVEL DELACRUZ |
| Quality Review Completed | 12/7/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 12/8/2023 | APPLICANT |
| Applicant returned to address corrections | 5/24/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 5/29/2024 | MARVEL DELACRUZ |
| Issued | 5/29/2024 | APPLICANT |
| CofO in Progress | 3/24/2025 | MATTHEW NELSON |
| CofO in Progress | 3/24/2025 | MATTHEW NELSON |
| CofO in Progress | 5/23/2025 | RAUL OLAGI |
| Permit Finaled | 6/3/2025 | RUBEN SALAS |
| CofO Issued | 6/3/2025 | RUBEN SALAS |
| Permit Finaled | 6/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/11/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 12/22/2023 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 5/14/2024 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 5/15/2024 | EDGAR ALCARAZ |
| Senate Bill 9 | Cleared | 5/17/2024 | DORIAN AGUILAR |
| Miscellaneous | Cleared | 5/24/2024 | MIGUEL CRISOSTOMO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/8/2024 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 7/23/2024 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 8/6/2024 | Corrections Issued | MATTHEW NELSON |
| Deputy Reinf. Concrete | 8/7/2024 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 8/29/2024 | Approved | MATTHEW NELSON |
| Wood Frame | 8/29/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 10/17/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 10/17/2024 | Approved | MATTHEW NELSON |
| Underground Mechanical | 10/17/2024 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/29/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 10/29/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 10/29/2024 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 10/29/2024 | Approved | MATTHEW NELSON |
| Insulation | 11/4/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/4/2024 | Partial Approval | MATTHEW NELSON |
| Drywall Nailing | 11/8/2024 | No Access for Inspection | LOUIS ESCOTO |
| Shower Pan | 11/8/2024 | No Access for Inspection | LOUIS ESCOTO |
| Drywall Nailing | 11/13/2024 | Approved | MICHAEL CORTEZ |
| Shower Pan | 11/13/2024 | Corrections Issued | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 11/20/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 11/20/2024 | Approved | MATTHEW NELSON |
| Final | 2/14/2025 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/14/2025 | Approved | MATTHEW NELSON |
| Green Building Final | 2/14/2025 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/14/2025 | SGSOV Not Required | MATTHEW NELSON |
| Service/Power Release | 2/14/2025 | Corrections Issued | MATTHEW NELSON |
| Smoke Detectors | 2/14/2025 | Approved | MATTHEW NELSON |
| Final | 3/21/2025 | Corrections Issued | MATTHEW NELSON |
| Service/Power Release | 3/21/2025 | Approved | MATTHEW NELSON |
| Final | 3/24/2025 | Corrections Issued | MATTHEW NELSON |
| Final | 5/23/2025 | OK to Issue CofO | RAUL OLAGI |