15212 W CHATSWORTH ST 91345

Certificate Information: 15212 W CHATSWORTH ST 91345

Application / Permit
23010-20000-04557
Plan Check / Job No.
B23VN15624
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) IRR. SHAPED 35'-9" x 43'-5" DET. ONE-STORY ACCESSORY DWELLING UNIT [PER LAMC 12.22 A.33 (c)-(d)]; NFPA-13D THRU-OUT
Permit Issued
Issued on 7/24/2024
Issuing Office
Current Status
CofO Issued on 5/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2023 APPLICANT
Assigned to Plan Check Engineer 11/30/2023 SEAN SHAHMIRI
Corrections Issued 12/4/2023 SEAN SHAHMIRI
Quality Review Completed 12/7/2023 STEVEN KIM
Applicant returned to address corrections 4/19/2024 SEAN SHAHMIRI
Applicant returned to address corrections 5/1/2024 SEAN SHAHMIRI
Plan Check Approved 5/6/2024 SEAN SHAHMIRI
Plan Check Approved 7/23/2024 ALFRED RAMIREZ
Issued 7/24/2024 APPLICANT
CofO in Progress 5/8/2025 JENNIFER RABUCHIN
Permit Finaled 5/27/2025 RUBEN SALAS
CofO Issued 5/27/2025 RUBEN SALAS
Permit Finaled 5/27/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/13/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 1/2/2024 NIKKI ZULUETA
Sewer availability Cleared 1/29/2024 CARLOS AGUILERA
Hydrant and Access approval Cleared 2/3/2024 MATTHEW CRAIG
Low Impact Development (LID) Cleared 4/3/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 4/5/2024 EDGAR ALCARAZ
Construction near power lines Cleared 7/18/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/26/2024 Not Ready for Inspection JENNIFER RABUCHIN
Pre-Inspection 7/26/2024 Not Ready for Inspection JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 8/16/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/26/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/26/2024 Partial Approval JENNIFER RABUCHIN
Insulation 8/27/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/28/2024 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 9/23/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/23/2024 Partial Approval VINCENT HANLEY
MERV13>=Rough 9/23/2024 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 9/23/2024 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 10/8/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 10/8/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/22/2024 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 10/22/2024 Partial Approval JENNIFER RABUCHIN
Wood Frame 10/22/2024 Approved JENNIFER RABUCHIN
Insulation 10/29/2024 Corrections Issued MICHAEL CORTEZ
Drywall Nailing 11/5/2024 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Partial Inspection JENNIFER RABUCHIN
Shower Pan 12/4/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/9/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/6/2025 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 3/26/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 3/26/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 3/26/2025 Approved ROBERTO PALACIOS-LOPEZ
MERV13>=Final 3/26/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
MERV13>=Rough 3/26/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 3/26/2025 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 3/26/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 3/26/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 3/26/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 4/2/2025 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 4/2/2025 Not Ready for Inspection JENNIFER RABUCHIN
Service/Power Release 4/2/2025 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 4/2/2025 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 5/6/2025 Approved JENNIFER RABUCHIN
Final 5/6/2025 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 5/6/2025 Approved JENNIFER RABUCHIN
MERV13>=Final 5/6/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/6/2025 Approved JENNIFER RABUCHIN
Service/Power Release 5/6/2025 Approved JENNIFER RABUCHIN
Smoke Detectors 5/6/2025 Approved JENNIFER RABUCHIN