17126 W HORACE ST 91344

Certificate Information: 17126 W HORACE ST 91344

Application / Permit
23010-20000-04549
Plan Check / Job No.
B23VN14649
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New 1-story Accessory Dwelling Unit (39'-10.25" x 19'-11") per CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33(c)-(d), (g)
Permit Issued
Issued on 4/26/2024
Issuing Office
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 VAHAN JIVALAGIAN
Corrections Issued 11/12/2023 VAHAN JIVALAGIAN
Quality Review Completed 11/20/2023 OMID HEDAYAT
Applicant returned to address corrections 1/19/2024 VAHAN JIVALAGIAN
Plan Check Approved 4/25/2024 VAHAN JIVALAGIAN
Issued 4/26/2024 APPLICANT
CofO in Progress 10/11/2024 STEVEN BACK
CofO Issued 10/25/2024 JOHN JANSON
Permit Finaled 10/25/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/17/2023 LEE GUILBEAUX
Construction near power lines Cleared 3/26/2024 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 4/11/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 4/11/2024 ROGELIO CORTES
Sewer availability Cleared 4/11/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/12/2024 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/8/2024 Partial Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 5/23/2024 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 5/31/2024 Not Ready for Inspection STEVEN BACK
Footing/Foundation/Slab 5/31/2024 Not Ready for Inspection STEVEN BACK
Sewer 5/31/2024 Approved STEVEN BACK
Footing/Foundation/Slab 6/13/2024 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 6/13/2024 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 6/14/2024 Corrections Issued HENRY KIM
Footing/Foundation/Slab 6/14/2024 Approved HENRY KIM
PLUMBING-Rough 6/14/2024 Approved HENRY KIM
ELECTRICAL-Rough 6/27/2024 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/27/2024 Corrections Issued STEVEN BACK
HVAC-Rough 6/27/2024 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 7/2/2024 Partial Approval JEFFREY PARD
Deputy Wood Construction 7/2/2024 Conditional Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/2/2024 Approved JEFFREY PARD
Green Building Rough 7/2/2024 Approved JEFFREY PARD
Interior/Exterior Lathing 7/2/2024 Approved JEFFREY PARD
Shower Pan 7/2/2024 Approved JEFFREY PARD
Verify Sprinkler Sign Off 7/2/2024 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 7/8/2024 Approved JEFFREY PARD
Insulation 7/8/2024 Approved JEFFREY PARD
Interior/Exterior Lathing 7/11/2024 Approved HENRY KIM
Drywall Nailing 7/18/2024 Approved STEVEN BACK
HVAC-Rough 7/31/2024 Approved JEFFREY PARD
Final 9/6/2024 Corrections Issued STEVEN BACK
Green Building Final 9/6/2024 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 9/6/2024 SGSOV Not Required STEVEN BACK
Smoke Detectors 9/6/2024 Approved STEVEN BACK
Final 9/19/2024 Not Ready for Inspection STEVEN BACK
Final 10/11/2024 OK to Issue CofO STEVEN BACK
Service/Power Release 10/11/2024 Approved STEVEN BACK