18417 W CHATSWORTH ST 91326

Certificate Information: 18417 W CHATSWORTH ST 91326

Application / Permit
23010-20000-04515
Plan Check / Job No.
B23VN15525
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 26'-11" x 49'-0" IRREGULAR SHAPED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (d) WITH ATTACHED 12'-8" x 4'-4" COVERED PORCH. WORK PER WFPP
Permit Issued
Issued on 7/23/2024
Issuing Office
Current Status
Issued on 7/23/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/9/2023 APPLICANT
Assigned to Plan Check Engineer 11/14/2023 MIROOSH KHACHATOORIAN
Corrections Issued 11/15/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 2/21/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 3/16/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 3/19/2024 ALFRED RAMIREZ
Issued 7/23/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/18/2023 COLIN LOREDO
Low Impact Development (LID) Cleared 2/15/2024 ROGELIO CORTES
Eng Process Fee Ord 176,300 Cleared 2/16/2024 BRYAN GODINEZ
Roof/Waste drainage to street Cleared 2/16/2024 BRYAN GODINEZ
Sewer availability Cleared 2/16/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/3/2024 Approved DAVID SCANTLIN
PLUMBING-Rough 1/7/2025 Partial Approval DAVID SCANTLIN
Deputy Reinf. Concrete 1/21/2025 Conditional Approval DAVID SCANTLIN
Footing/Foundation/Slab 1/24/2025 No Access for Inspection DAVID SCANTLIN
Footing/Foundation/Slab 1/31/2025 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Approved DAVID SCANTLIN
Green Building Rough 5/12/2025 Not Ready for Inspection DAVID SCANTLIN
Verify Sprinkler Sign Off 5/12/2025 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 8/11/2025 Approved DAVID SCANTLIN
ELECTRICAL-Rough 8/11/2025 Approved DAVID SCANTLIN
Green Building Rough 8/11/2025 Approved DAVID SCANTLIN
HVAC-Rough 8/11/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 8/11/2025 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 8/11/2025 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 8/11/2025 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 8/11/2025 Approved DAVID SCANTLIN
Insulation 10/16/2025 Corrections Issued DAVID SCANTLIN
Drywall Nailing 1/8/2026 No Access for Inspection DAVID SCANTLIN
Drywall Nailing 1/12/2026 Approved KRISTEN CAUSEY