17147 W KINGSBURY ST 91344

Certificate Information: 17147 W KINGSBURY ST 91344

Application / Permit
23010-20000-04505
Plan Check / Job No.
B23VN15499
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: New A.D.U.
Permit Issued
Issued on 7/30/2024
Issuing Office
Current Status
Issued on 7/30/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/19/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 ARSALAN SHABESTARI
Corrections Issued 12/18/2023 ARSALAN SHABESTARI
Quality Review Completed 1/3/2024 YOUNG KIM
Plan Check Approved 7/29/2024 ARSALAN SHABESTARI
Issued 7/30/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/17/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/22/2024 CARLOS AGUILERA
Sewer availability Cleared 1/22/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 4/23/2024 SAMUEL LINN
Hydrant and Access approval Cleared 7/5/2024 KURT CORRAL
Roof/Waste drainage to street Cleared 7/6/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/6/2024 Approved JAVIER RAMOS JR
Underground Mechanical 10/4/2024 Corrections Issued JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 10/23/2024 Approved MISAEL ESPARZA
Footing/Foundation/Slab 10/23/2024 Approved MISAEL ESPARZA
PLUMBING-Rough 10/23/2024 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 2/21/2025 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 2/21/2025 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/21/2025 Approved JAVIER RAMOS JR
Green Building Rough 2/21/2025 Approved JAVIER RAMOS JR
HVAC-Rough 2/21/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 2/21/2025 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 3/27/2025 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 3/27/2025 Partial Approval CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 3/27/2025 Partial Inspection CHRISTOPHER ROJAS
Shower Pan 3/27/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/2/2025 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/8/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/8/2025 Approved CHRISTOPHER ROJAS
Insulation 4/8/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 4/17/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 4/17/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 5/13/2025 Corrections Issued CHRISTOPHER ROJAS
Sewer 5/20/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 5/20/2025 Approved CHRISTOPHER ROJAS
Pre-Inspection 7/10/2026 Approved CHRISTOPHER ROJAS