7313 N KENTLAND AVE 91307
Certificate Information: 7313 N KENTLAND AVE 91307
- Application / Permit
- 23010-20000-04498
- Plan Check / Job No.
- B23VN15464
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. New detached 1200 SF (35' x 17') 2 story with roof deck ADU per LAMC 12.22 A33 (c) and (d)
- Permit Issued
- Issued on 1/17/2024
- Issuing Office
- Current Status
- CofO Issued on 5/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | NGHI SU |
| Corrections Issued | 11/18/2023 | NGHI SU |
| Quality Review Completed | 12/1/2023 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 12/15/2023 | NGHI SU |
| Plan Check Approved | 1/12/2024 | NGHI SU |
| Issued | 1/17/2024 | APPLICANT |
| CofO in Progress | 5/6/2025 | CHRIS CHRISTENSEN |
| Permit Finaled | 5/14/2025 | JOHN JANSON |
| CofO Issued | 5/14/2025 | JOHN JANSON |
| Permit Finaled | 5/14/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/11/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/11/2023 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 12/20/2023 | WALTER RAMIREZ |
| Low Impact Development (LID) | Cleared | 12/20/2023 | SHAHIN KHAZEY |
| Roof/Waste drainage to street | Cleared | 12/20/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manesh,, Behnam Abraham; Lic. No.: C38454 | 17337 VENTURA BLVD STE 310 ENCINO, CA 91316 |
| Engineer | Manesh,, Behnam Abraham; Lic. No.: NA38454 | , |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/23/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Sewer | 1/23/2024 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/29/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 1/31/2024 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2024 | Partial Approval | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2024 | Approved | CHRIS CHRISTENSEN |
| Special/Order Compliance | 2/22/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 3/13/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 3/13/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/13/2024 | Approved | CHRIS CHRISTENSEN |
| Special/Order Compliance | 3/13/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 3/20/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 3/20/2024 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 3/20/2024 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/22/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 3/22/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 3/26/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 3/28/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 4/17/2024 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 4/22/2024 | Partial Approval | JEFFREY HARTLINE |
| Underground Mechanical | 10/3/2024 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/7/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 11/7/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 11/7/2024 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/7/2024 | SGSOV Not Required | CHRIS CHRISTENSEN |
| Service/Power Release | 11/7/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 11/7/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 3/3/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Service/Power Release | 3/3/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Deck | 3/18/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 3/18/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Deck | 3/28/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Final | 3/28/2025 | Approved | CHRIS CHRISTENSEN |
| Deck | 4/2/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 4/2/2025 | Approved | JEFFREY HARTLINE |
| Deck | 4/15/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 5/5/2025 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Service/Power Release | 5/5/2025 | Approved | CHRIS CHRISTENSEN |