11316 N WHITE OAK AVE 91344

Certificate Information: 11316 N WHITE OAK AVE 91344

Application / Permit
23010-20000-04492
Plan Check / Job No.
B23VN15445
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 30'-6" X 41'-9" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 6/15/2024
Issuing Office
Current Status
CofO Issued on 3/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2023 APPLICANT
Assigned to Plan Check Engineer 11/13/2023 ISIS ARGUETA
Corrections Issued 11/14/2023 ISIS ARGUETA
Applicant returned to address corrections 3/15/2024 ALEC MOUSAKHANIAN
Plan Check Approved 4/11/2024 ALEC MOUSAKHANIAN
Issued 6/15/2024 APPLICANT
CofO in Progress 2/27/2025 STEVEN BACK
Permit Finaled 3/11/2025 JOHN JANSON
CofO Issued 3/11/2025 JOHN JANSON
Permit Finaled 3/11/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/9/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/9/2024 CARLOS AGUILERA
Sewer availability Cleared 1/9/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 3/4/2024 TOMMY YIN
Construction near power lines Cleared 3/5/2024 OSCAR CASTRO
Roof/Waste drainage to street Cleared 3/6/2024 CARLOS RAMIREZ
Grading Pre-Inspection Cleared 4/11/2024 ALEC MOUSAKHANIAN

Contact Information

Contractor Simoni John Ioan; Lic. No.: 620256-B       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/16/2024 Approved STEVEN BACK
PLUMBING-Rough 7/16/2024 Partial Approval STEVEN BACK
Pre-Inspection 7/16/2024 Partial Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 8/29/2024 Approved STEVEN BACK
HVAC-Rough 8/29/2024 Approved STEVEN BACK
MERV13>=Rough 8/29/2024 Approved STEVEN BACK
BUILDING-Rough-Frame 9/24/2024 Approved TROY SANDERS
ELECTRICAL-Rough 9/24/2024 Approved TROY SANDERS
Green Building Rough 9/24/2024 Approved TROY SANDERS
Interior/Exterior Lathing 9/24/2024 Partial Approval TROY SANDERS
PLUMBING-Rough 9/24/2024 Approved TROY SANDERS
Sewer 9/24/2024 Approved TROY SANDERS
Shower Pan 9/24/2024 Approved TROY SANDERS
Verify Sprinkler Sign Off 9/24/2024 Approved TROY SANDERS
Insulation 10/3/2024 Approved STEVEN BACK
Drywall Nailing 10/8/2024 Approved STEVEN BACK
Interior/Exterior Lathing 10/8/2024 Approved STEVEN BACK
ELECTRICAL-Final 1/28/2025 Approved STEVEN BACK
Final 1/28/2025 Corrections Issued STEVEN BACK
Green Building Final 1/28/2025 Approved STEVEN BACK
HVAC-Final 1/28/2025 Approved STEVEN BACK
MERV13>=Final 1/28/2025 Approved STEVEN BACK
PLUMBING-Final 1/28/2025 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Not Required STEVEN BACK
Smoke Detectors 1/28/2025 Approved STEVEN BACK
Final 2/24/2025 Corrections Issued STEVEN BACK
Final 2/27/2025 OK to Issue CofO STEVEN BACK
Service/Power Release 2/27/2025 Approved STEVEN BACK