12506 1/2 W CORRENTI ST 91331
Certificate Information: 12506 1/2 W CORRENTI ST 91331
- Application / Permit
- 23010-20000-04484
- Plan Check / Job No.
- B23VN15408
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SFD PER SB9 TWO UNIT DEVELOPMENT (1-STORY)
- Permit Issued
- Issued on 3/15/2024
- Issuing Office
- Current Status
- CofO Issued on 10/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | CARLOS MONTES |
| Corrections Issued | 11/29/2023 | CARLOS MONTES |
| Quality Review Completed | 12/1/2023 | GARO TELMI |
| Plan Check Approved | 3/13/2024 | CARLOS MONTES |
| Issued | 3/15/2024 | APPLICANT |
| CofO in Progress | 10/9/2025 | MICHEL ABAJAN |
| CofO Issued | 10/23/2025 | RUBEN SALAS |
| Permit Finaled | 10/23/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/1/2023 | CARLOS AGUILERA |
| ZI | Cleared | 12/4/2023 | NATHAN ROMINE |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/6/2023 | CARLOS AGUILERA |
| Clean Up Green Up | Cleared | 1/25/2024 | NATHAN ROMINE |
| Senate Bill 9 | Cleared | 1/25/2024 | NATHAN ROMINE |
| Low Impact Development (LID) | Cleared | 2/26/2024 | TOMMY YIN |
| Hydrant and Access approval | Cleared | 3/2/2024 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 3/2/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hakhamaneshi,, Manouchehr; Lic. No.: C88083 | 12935 ALCOSTA BLVD PO BOX 1435 SAN RAMON, CA 94583 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/30/2024 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/14/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2024 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 10/29/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 10/29/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 11/13/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/13/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/4/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 12/4/2024 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 12/4/2024 | Approved | MICHEL ABAJAN |
| Insulation | 12/20/2024 | Conditional Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/20/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 12/26/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/3/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 4/3/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/3/2025 | Approved | MICHEL ABAJAN |
| Final | 7/15/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/15/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/15/2025 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 7/15/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 7/15/2025 | Approved | MICHEL ABAJAN |
| Final | 10/8/2025 | OK to Issue CofO | MICHEL ABAJAN |