12506 1/2 W CORRENTI ST 91331

Certificate Information: 12506 1/2 W CORRENTI ST 91331

Application / Permit
23010-20000-04484
Plan Check / Job No.
B23VN15408
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD PER SB9 TWO UNIT DEVELOPMENT (1-STORY)
Permit Issued
Issued on 3/15/2024
Issuing Office
Current Status
CofO Issued on 10/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2023 APPLICANT
Assigned to Plan Check Engineer 11/21/2023 CARLOS MONTES
Corrections Issued 11/29/2023 CARLOS MONTES
Quality Review Completed 12/1/2023 GARO TELMI
Plan Check Approved 3/13/2024 CARLOS MONTES
Issued 3/15/2024 APPLICANT
CofO in Progress 10/9/2025 MICHEL ABAJAN
CofO Issued 10/23/2025 RUBEN SALAS
Permit Finaled 10/23/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/1/2023 CARLOS AGUILERA
ZI Cleared 12/4/2023 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 12/5/2023 CARLOS AGUILERA
Sewer availability Cleared 12/6/2023 CARLOS AGUILERA
Clean Up Green Up Cleared 1/25/2024 NATHAN ROMINE
Senate Bill 9 Cleared 1/25/2024 NATHAN ROMINE
Low Impact Development (LID) Cleared 2/26/2024 TOMMY YIN
Hydrant and Access approval Cleared 3/2/2024 GILBERT URREA
Roof/Waste drainage to street Cleared 3/2/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Hakhamaneshi,, Manouchehr; Lic. No.: C88083 12935 ALCOSTA BLVD   PO BOX 1435    SAN RAMON, CA 94583

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/30/2024 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 6/14/2024 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 10/29/2024 Approved MICHEL ABAJAN
HVAC-Rough 10/29/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/13/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 11/13/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 12/4/2024 Approved MICHEL ABAJAN
Green Building Rough 12/4/2024 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 12/4/2024 Approved MICHEL ABAJAN
Insulation 12/20/2024 Conditional Approval MICHEL ABAJAN
Interior/Exterior Lathing 12/20/2024 Approved MICHEL ABAJAN
Drywall Nailing 12/26/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/3/2025 Approved MICHEL ABAJAN
HVAC-Final 4/3/2025 Approved MICHEL ABAJAN
PLUMBING-Final 4/3/2025 Approved MICHEL ABAJAN
Final 7/15/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 7/15/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/15/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 7/15/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 7/15/2025 Approved MICHEL ABAJAN
Final 10/8/2025 OK to Issue CofO MICHEL ABAJAN