13564 W POLK ST 91342

Certificate Information: 13564 W POLK ST 91342

Application / Permit
23010-20000-04483
Plan Check / Job No.
B23VN15403
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-story (30' x 20') Accessory Dwelling Unit per LAMC 12.22 A.33 (c) - (d)
Permit Issued
Issued on 1/19/2024
Issuing Office
Current Status
CofO Issued on 1/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 VAHAN JIVALAGIAN
Corrections Issued 11/22/2023 VAHAN JIVALAGIAN
Quality Review Completed 11/22/2023 OMID HEDAYAT
Building Plans Picked Up 12/27/2023 APPLICANT
Applicant returned to address corrections 1/18/2024 VAHAN JIVALAGIAN
Plan Check Approved 1/19/2024 VAHAN JIVALAGIAN
Issued 1/19/2024 APPLICANT
CofO in Progress 12/31/2024 KEVIN BERBERYAN
CofO Issued 1/17/2025 RUBEN SALAS
Permit Finaled 1/17/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/1/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/12/2023 EDGAR ALCARAZ
Sewer availability Cleared 12/12/2023 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 1/12/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 1/12/2024 EDGAR ALCARAZ
Hydrant and Access approval Cleared 1/16/2024 LAVEON RIDER
GPI Written Notices Cleared 1/19/2024 VAHAN JIVALAGIAN
Grading Pre-Inspection Cleared 1/19/2024 VAHAN JIVALAGIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/20/2024 Approved THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 2/28/2024 Not Ready for Inspection KEVIN BERBERYAN
Pre-Inspection 2/28/2024 Partial Inspection KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 3/22/2024 Partial Approval KEVIN BERBERYAN
Sewer 3/22/2024 Approved KEVIN BERBERYAN
Underground Mechanical 3/22/2024 Approved KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 4/10/2024 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 4/10/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 4/23/2024 Conditional Approval KEVIN BERBERYAN
Green Building Rough 4/23/2024 Not Ready for Inspection KEVIN BERBERYAN
Verify Sprinkler Sign Off 4/23/2024 Approved KEVIN BERBERYAN
Wood Frame 4/23/2024 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 5/3/2024 Partial Approval KEVIN BERBERYAN
Green Building Rough 5/3/2024 Not Ready for Inspection KEVIN BERBERYAN
Wood Frame 5/3/2024 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 5/29/2024 Partial Approval KEVIN BERBERYAN
ELECTRICAL-Rough 5/29/2024 Approved KEVIN BERBERYAN
HVAC-Rough 5/29/2024 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 5/29/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 6/4/2024 Corrections Issued KEVIN BERBERYAN
Green Building Rough 6/4/2024 Approved KEVIN BERBERYAN
HVAC-Rough 6/4/2024 Approved KEVIN BERBERYAN
Insulation 6/4/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 6/4/2024 Approved KEVIN BERBERYAN
Drywall Nailing 6/10/2024 Approved KEVIN BERBERYAN
Shower Pan 6/26/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 7/5/2024 Approved KEVIN BERBERYAN
Smoke Detectors 9/9/2024 Not Ready for Inspection KEVIN BERBERYAN
Underground Mechanical 9/9/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 9/16/2024 Partial Inspection KEVIN BERBERYAN
Green Building Final 10/8/2024 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 10/8/2024 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 12/6/2024 Approved RAUL OLAGI
Deputy Wood Construction 12/6/2024 Conditional Approval RAUL OLAGI
ELECTRICAL-Final 12/6/2024 Corrections Issued RAUL OLAGI
Final 12/6/2024 Corrections Issued RAUL OLAGI
Green Building Final 12/6/2024 Approved RAUL OLAGI
HVAC-Final 12/6/2024 Approved RAUL OLAGI
PLUMBING-Final 12/6/2024 Approved RAUL OLAGI
Smoke Detectors 12/6/2024 Corrections Issued RAUL OLAGI
Final 12/17/2024 OK to Issue CofO KEVIN BERBERYAN
Smoke Detectors 12/17/2024 Approved KEVIN BERBERYAN