13564 W POLK ST 91342
Certificate Information: 13564 W POLK ST 91342
- Application / Permit
- 23010-20000-04483
- Plan Check / Job No.
- B23VN15403
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story (30' x 20') Accessory Dwelling Unit per LAMC 12.22 A.33 (c) - (d)
- Permit Issued
- Issued on 1/19/2024
- Issuing Office
- Current Status
- CofO Issued on 1/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | VAHAN JIVALAGIAN |
| Corrections Issued | 11/22/2023 | VAHAN JIVALAGIAN |
| Quality Review Completed | 11/22/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 12/27/2023 | APPLICANT |
| Applicant returned to address corrections | 1/18/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 1/19/2024 | VAHAN JIVALAGIAN |
| Issued | 1/19/2024 | APPLICANT |
| CofO in Progress | 12/31/2024 | KEVIN BERBERYAN |
| CofO Issued | 1/17/2025 | RUBEN SALAS |
| Permit Finaled | 1/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/1/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 12/12/2023 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 1/12/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 1/12/2024 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 1/16/2024 | LAVEON RIDER |
| GPI Written Notices | Cleared | 1/19/2024 | VAHAN JIVALAGIAN |
| Grading Pre-Inspection | Cleared | 1/19/2024 | VAHAN JIVALAGIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/20/2024 | Approved | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 2/28/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Pre-Inspection | 2/28/2024 | Partial Inspection | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 3/22/2024 | Partial Approval | KEVIN BERBERYAN |
| Sewer | 3/22/2024 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 3/22/2024 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 4/10/2024 | Approved | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 4/10/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 4/23/2024 | Conditional Approval | KEVIN BERBERYAN |
| Green Building Rough | 4/23/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 4/23/2024 | Approved | KEVIN BERBERYAN |
| Wood Frame | 4/23/2024 | Partial Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 5/3/2024 | Partial Approval | KEVIN BERBERYAN |
| Green Building Rough | 5/3/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Wood Frame | 5/3/2024 | Partial Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 5/29/2024 | Partial Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 5/29/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 5/29/2024 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 5/29/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/4/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 6/4/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 6/4/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 6/4/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 6/4/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 6/10/2024 | Approved | KEVIN BERBERYAN |
| Shower Pan | 6/26/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 7/5/2024 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 9/9/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Underground Mechanical | 9/9/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 9/16/2024 | Partial Inspection | KEVIN BERBERYAN |
| Green Building Final | 10/8/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Smoke Detectors | 10/8/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 12/6/2024 | Approved | RAUL OLAGI |
| Deputy Wood Construction | 12/6/2024 | Conditional Approval | RAUL OLAGI |
| ELECTRICAL-Final | 12/6/2024 | Corrections Issued | RAUL OLAGI |
| Final | 12/6/2024 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 12/6/2024 | Approved | RAUL OLAGI |
| HVAC-Final | 12/6/2024 | Approved | RAUL OLAGI |
| PLUMBING-Final | 12/6/2024 | Approved | RAUL OLAGI |
| Smoke Detectors | 12/6/2024 | Corrections Issued | RAUL OLAGI |
| Final | 12/17/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| Smoke Detectors | 12/17/2024 | Approved | KEVIN BERBERYAN |