6600 N GLORIA AVE 91406

Certificate Information: 6600 N GLORIA AVE 91406

Application / Permit
23010-20000-04450
Plan Check / Job No.
B23VN15297
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 19'-11" x 25'-0" RECREATION ROOM.
Permit Issued
Issued on 11/15/2023
Issuing Office
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2023 APPLICANT
Assigned to Plan Check Engineer 11/6/2023 GIOVANNY CHAVEZ
Corrections Issued 11/6/2023 GIOVANNY CHAVEZ
Issued 11/15/2023 APPLICANT
CofO in Progress 12/13/2024 SALVADOR MARTINEZ
CofO in Progress 1/9/2025 RAUL OLAGI
CofO in Progress 2/8/2025 RAUL OLAGI
Permit Finaled 2/18/2025 RUBEN SALAS
CofO Issued 2/18/2025 RUBEN SALAS
Permit Finaled 2/18/2025 RUBEN SALAS

Permit Application Clearance Information

ZI Cleared 11/7/2023 NELSON RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 11/9/2023 NIKKI ZULUETA
Low Impact Development (LID) Cleared 11/9/2023 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 11/9/2023 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/2/2024 Corrections Issued JOHN COLEMAN
PLUMBING-Rough 1/2/2024 Not Ready for Inspection JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 1/18/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 3/6/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 3/13/2024 Approved RAUL OLAGI
ELECTRICAL-Rough 3/13/2024 Approved RAUL OLAGI
Green Building Rough 3/13/2024 Approved RAUL OLAGI
HVAC-Rough 3/13/2024 Partial Approval RAUL OLAGI
PLUMBING-Rough 3/13/2024 Approved RAUL OLAGI
Verify Sprinkler Sign Off 3/13/2024 Approved RAUL OLAGI
Insulation 3/15/2024 Approved RAUL OLAGI
Sewer 3/15/2024 Corrections Issued RAUL OLAGI
Drywall Nailing 3/27/2024 Approved SALVADOR MARTINEZ
Final 11/18/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 11/18/2024 Not Ready for Inspection SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 11/18/2024 SGSOV Approved SALVADOR MARTINEZ
Service/Power Release 11/18/2024 Not Ready for Inspection SALVADOR MARTINEZ
Smoke Detectors 11/18/2024 Partial Approval SALVADOR MARTINEZ
Final 11/22/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 11/22/2024 Not Ready for Inspection SALVADOR MARTINEZ
Service/Power Release 11/22/2024 Partial Inspection SALVADOR MARTINEZ
Smoke Detectors 11/22/2024 Approved SALVADOR MARTINEZ
Final 12/2/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 12/2/2024 Corrections Issued SALVADOR MARTINEZ
Service/Power Release 12/2/2024 Not Ready for Inspection SALVADOR MARTINEZ
Final 12/6/2024 Corrections Issued SALVADOR MARTINEZ
Final 12/13/2024 OK to Issue CofO SALVADOR MARTINEZ
Green Building Final 12/13/2024 Approved SALVADOR MARTINEZ
Special/Order Compliance 1/9/2025 Corrections Issued RAUL OLAGI