17826 W TRIBUNE ST 91344

Certificate Information: 17826 W TRIBUNE ST 91344

Application / Permit
23010-20000-04449
Plan Check / Job No.
B23VN15292
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 41' X 24' ONE STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING NFPA 13R REQUIRED THROUGHOUT
Permit Issued
Issued on 2/27/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 11/14/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 11/14/2023 STEVEN KIM
Building Plans Picked Up 11/15/2023 APPLICANT
Applicant returned to address corrections 2/9/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 2/27/2024 SEWADA ZADOORAN MILAGARDI
Issued 2/27/2024 APPLICANT
CofO in Progress 9/23/2024 STEVEN BACK
CofO Issued 9/30/2024 JOHN JANSON
Permit Finaled 9/30/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/27/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/28/2023 LEE GUILBEAUX
Sewer availability Cleared 11/28/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/28/2023 LEE GUILBEAUX
Hydrant and Access approval Cleared 2/13/2024 KURT CORRAL
Low Impact Development (LID) Cleared 2/16/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 2/20/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/4/2024 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 3/5/2024 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Partial Approval STEVEN BACK
PLUMBING-Rough 4/5/2024 Approved JOHN KIDWELL
ELECTRICAL-Rough 4/22/2024 Approved STEVEN BACK
HVAC-Rough 4/24/2024 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 5/1/2024 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Approved STEVEN BACK
Green Building Rough 5/1/2024 Approved STEVEN BACK
HVAC-Rough 5/1/2024 Approved STEVEN BACK
Interior/Exterior Lathing 5/1/2024 Partial Approval STEVEN BACK
Verify Sprinkler Sign Off 5/1/2024 Approved STEVEN BACK
Insulation 5/3/2024 Approved STEVEN BACK
Drywall Nailing 5/10/2024 Approved STEVEN BACK
Interior/Exterior Lathing 5/10/2024 Approved STEVEN BACK
Final 8/28/2024 Corrections Issued STEVEN BACK
Green Building Final 8/28/2024 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 8/28/2024 SGSOV Not Required STEVEN BACK
Service/Power Release 8/28/2024 Not Required STEVEN BACK
Smoke Detectors 8/28/2024 Approved STEVEN BACK
Special/Order Compliance 8/29/2024 Corrections Issued STEVEN BACK
ELECTRICAL-Final 9/23/2024 Approved STEVEN BACK
Final 9/23/2024 OK to Issue CofO STEVEN BACK