2436 E SHOREDALE AVE 90031
Certificate Information: 2436 E SHOREDALE AVE 90031
- Application / Permit
- 23010-20000-04441
- Plan Check / Job No.
- B23VN15273
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 24' X 24'-5" 2-STORY DETACHED SFD per SB9 Two-Unit Development Ca Govt Code 65852.21. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/18/2024
- Issuing Office
- Current Status
- CofO Issued on 7/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | RAPHAEL ROSAS |
| Corrections Issued | 11/21/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 11/30/2023 | STEVEN KIM |
| Building Plans Picked Up | 12/5/2023 | APPLICANT |
| Applicant returned to address corrections | 2/9/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 12/17/2024 | RAPHAEL ROSAS |
| Issued | 12/18/2024 | APPLICANT |
| CofO in Progress | 7/24/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 7/25/2025 | DEROLD HAUFF |
| CofO Issued | 7/25/2025 | DEROLD HAUFF |
| Permit Finaled | 7/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/21/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 12/26/2023 | TREVOR QUAN |
| ZI | Cleared | 1/24/2024 | NATHAN ROMINE |
| Low Impact Development (LID) | Cleared | 2/2/2024 | TOMMY YIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 2/5/2024 | WALLIE JONG |
| Senate Bill 9 | Cleared | 10/15/2024 | BRENNEN OBETO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 12/31/2024 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 12/31/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/3/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Partial Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 2/3/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 2/3/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/4/2025 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 2/4/2025 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 2/24/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/24/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 2/24/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/24/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/24/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 2/24/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/6/2025 | Approved | FREDDIE RIVERA |
| Shower Pan | 3/6/2025 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 3/6/2025 | Approved | FREDDIE RIVERA |
| Wood Frame | 3/6/2025 | Partial Inspection | FREDDIE RIVERA |
| Insulation | 3/10/2025 | Corrections Issued | ANTHONY RAMOS |
| Drywall Nailing | 3/13/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 3/18/2025 | Approved | JOSH MEISTER |
| Underground Mechanical | 4/14/2025 | Partial Approval | ANTHONY RAMOS |
| Underground Mechanical | 4/22/2025 | Corrections Issued | BRENDAN MORELLI |
| Underground Mechanical | 4/28/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Final | 7/11/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 7/11/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/11/2025 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Service/Power Release | 7/11/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 7/11/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 7/21/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/21/2025 | SGSOV No Gas | HAMIK HARTOUNIAN |
| Service/Power Release | 7/21/2025 | Not Required | HAMIK HARTOUNIAN |