11005 N AMIGO AVE 91326

Certificate Information: 11005 N AMIGO AVE 91326

Application / Permit
23010-20000-04439
Plan Check / Job No.
B23VN15259
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
<ePLAN> (N) 29'6"X21'0" 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) TYPE VA CONSTRUCTION WITH NFPA 13R FIRE SPRINKLERS THROUGHOUT [ALL ELECTRIC BUILDING]
Permit Issued
Issued on 8/5/2024
Issuing Office
Current Status
CofO Issued on 1/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 MARVEL DELACRUZ
Corrections Issued 12/1/2023 MARVEL DELACRUZ
Quality Review Completed 12/6/2023 OMID HEDAYAT
Applicant returned to address corrections 5/2/2024 MARVEL DELACRUZ
Applicant returned to address corrections 6/27/2024 MARVEL DELACRUZ
Applicant returned to address corrections 7/31/2024 MARVEL DELACRUZ
Plan Check Approved 8/2/2024 OMID HEDAYAT
Issued 8/5/2024 APPLICANT
CofO in Progress 11/19/2025 DAVID SCANTLIN
Permit Finaled 1/23/2026 JOHN JANSON
CofO Issued 1/23/2026 JOHN JANSON
Permit Finaled 1/23/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/18/2023 EDGAR ALCARAZ
Watercourse Cleared 12/18/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/19/2023 EDGAR ALCARAZ
Sewer availability Cleared 12/19/2023 EDGAR ALCARAZ
Construction near power lines Cleared 3/20/2024 TINA MIRANDA
Construction within easement Cleared 3/20/2024 TINA MIRANDA
Hydrant and Access approval Cleared 4/25/2024 MATTHEW CRAIG
Distance to fire station Cleared 4/26/2024 MATTHEW CRAIG
Low Impact Development (LID) Cleared 5/30/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 6/1/2024 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Gosen,, James; Lic. No.: NA43590       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/28/2024 Corrections Issued DAVID SCANTLIN
Special/Order Compliance 8/28/2024 Approved SCOTT SOBEL
Footing/Foundation/Slab 9/12/2024 Corrections Issued DAVID SCANTLIN
Special/Order Compliance 9/12/2024 Approved HENRY KIM
Footing/Foundation/Slab 9/17/2024 Not Ready for Inspection DAVID SCANTLIN
Special/Order Compliance 9/17/2024 Approved HENRY KIM
Excavation/Setback/Form/Re-Bar 9/18/2024 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 10/21/2024 Approved DAVID SCANTLIN
Special/Order Compliance 10/21/2024 Partial Inspection HENRY KIM
PLUMBING-Rough 10/29/2024 Not Ready for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 10/30/2024 Partial Approval DAVID SCANTLIN
Insulation 10/30/2024 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Partial Approval DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 11/22/2024 Not Ready for Inspection DAVID SCANTLIN
Wood Frame 11/22/2024 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 12/2/2024 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 12/2/2024 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 12/2/2024 Not Ready for Inspection DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 12/2/2024 Partial Approval DAVID SCANTLIN
Verify Sprinkler Sign Off 12/2/2024 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 12/11/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 12/11/2024 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 12/11/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 1/10/2025 No Access for Inspection DAVID SCANTLIN
Green Building Rough 1/10/2025 No Access for Inspection DAVID SCANTLIN
Verify Sprinkler Sign Off 1/10/2025 No Access for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 1/14/2025 Approved DAVID SCANTLIN
Green Building Rough 1/14/2025 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 1/14/2025 Approved DAVID SCANTLIN
Insulation 1/16/2025 Not Ready for Inspection DAVID SCANTLIN
Insulation 1/21/2025 Approved DAVID SCANTLIN
Special/Order Compliance 1/21/2025 Partial Inspection JUAN ALVARADO
Drywall Nailing 1/27/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 2/19/2025 Partial Approval SCOTT SOBEL
Shower Pan 2/19/2025 Approved SCOTT SOBEL
Shower Pan 2/25/2025 Approved DAVID SCANTLIN
Final 4/24/2025 Corrections Issued DAVID SCANTLIN
Final 8/26/2025 Corrections Issued DAVID SCANTLIN
Green Building Final 8/26/2025 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Approved DAVID SCANTLIN
Service/Power Release 8/26/2025 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 8/26/2025 Approved DAVID SCANTLIN
ELECTRICAL-Final 11/18/2025 Approved DAVID SCANTLIN
Final 11/18/2025 OK to Issue CofO DAVID SCANTLIN
Green Building Final 11/18/2025 Approved DAVID SCANTLIN
HVAC-Final 11/18/2025 Approved DAVID SCANTLIN
PLUMBING-Final 11/18/2025 Approved DAVID SCANTLIN
Service/Power Release 11/18/2025 Approved DAVID SCANTLIN
Verify Rec and Parks Fee Memo 11/18/2025 Approved DAVID SCANTLIN