9943 N LEMONA AVE 91345

Certificate Information: 9943 N LEMONA AVE 91345

Application / Permit
23010-20000-04411
Plan Check / Job No.
B23VN15165
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-story Detached Accessory Dwelling Unit (30' x 23') per LAMC 12.22 A.33 (c) - (d).
Permit Issued
Issued on 12/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 VAHAN JIVALAGIAN
Corrections Issued 11/12/2023 VAHAN JIVALAGIAN
Quality Review Completed 11/16/2023 OMID HEDAYAT
Building Plans Picked Up 11/20/2023 APPLICANT
Plan Check Approved 12/14/2023 VAHAN JIVALAGIAN
Issued 12/14/2023 APPLICANT
CofO in Progress 10/24/2024 JENNIFER RABUCHIN
CofO in Progress 10/30/2024 ROBERT GOLD
CofO in Progress 10/31/2024 JENNIFER RABUCHIN
CofO Issued 11/14/2024 DANIEL ORRANTE
Permit Finaled 11/14/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/1/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/5/2023 EDGAR ALCARAZ
Sewer availability Cleared 12/5/2023 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 12/7/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 12/7/2023 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/9/2024 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 2/13/2024 Approved JENNIFER RABUCHIN
Wood Frame 3/11/2024 Corrections Issued JENNIFER RABUCHIN
Deputy Wood Construction 4/4/2024 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 4/16/2024 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 4/16/2024 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 4/16/2024 Approved JENNIFER RABUCHIN
Special/Order Compliance 4/16/2024 Corrections Issued JENNIFER RABUCHIN
Wood Frame 4/16/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/23/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 4/23/2024 Approved JENNIFER RABUCHIN
Green Building Rough 4/23/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 4/23/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 4/23/2024 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 4/23/2024 Approved JENNIFER RABUCHIN
Insulation 4/26/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/26/2024 Approved JENNIFER RABUCHIN
Shower Pan 4/26/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 5/1/2024 Approved JENNIFER RABUCHIN
Sewer 6/14/2024 Approved JENNIFER RABUCHIN
Underground Mechanical 6/14/2024 Partial Approval JENNIFER RABUCHIN
Service/Power Release 6/24/2024 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 7/17/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 7/17/2024 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 7/17/2024 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Final 7/25/2024 Corrections Issued JENNIFER RABUCHIN
Final 7/25/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 7/25/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 7/25/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 10/4/2024 Approved JENNIFER RABUCHIN
Final 10/4/2024 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 10/4/2024 Approved JENNIFER RABUCHIN
HVAC-Final 10/4/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/4/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/4/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 10/4/2024 Conditional Approval JENNIFER RABUCHIN
Smoke Detectors 10/4/2024 Approved JENNIFER RABUCHIN
Final 10/17/2024 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 10/17/2024 Approved JENNIFER RABUCHIN
Final 10/24/2024 OK to Issue CofO JENNIFER RABUCHIN