15859-15861 W LASSEN ST 91343
Certificate Information: 15859-15861 W LASSEN ST 91343
- Application / Permit
- 23010-20000-04404
- Plan Check / Job No.
- B23VN15145
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: PROPOSED 1ST FLOOR NEW ADU (1,115 S.F.) PER LAMC 12.22 A.33 (C)-(D) AND PROPOSED 2ND FLOOR NEW SB9 (800 S.F.) PER SB9 2 UNIT DEVELOPMENT CA GOVT CODE 65852.21
- Permit Issued
- Issued on 9/13/2024
- Issuing Office
- Current Status
- CofO Issued on 11/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | SUNMIN LEE |
| Corrections Issued | 11/22/2023 | SUNMIN LEE |
| Quality Review Completed | 12/5/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 7/18/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 7/19/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 8/30/2024 | SUNMIN LEE |
| Plan Check Approved | 9/12/2024 | SUNMIN LEE |
| Plan Check Approved | 9/13/2024 | SUNMIN LEE |
| Issued | 9/13/2024 | APPLICANT |
| CofO in Progress | 11/12/2025 | CHRISTOPHER ROJAS |
| CofO Issued | 11/21/2025 | RUBEN SALAS |
| Permit Finaled | 11/21/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 4/15/2024 | ERNEST TSE |
| Address approval | Cleared | 4/17/2024 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 6/4/2024 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 6/21/2024 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 7/9/2024 | EDGAR ALCARAZ |
| Miscellaneous | Cleared | 7/18/2024 | EDGAR ALCARAZ |
| GPI Written Notices | Cleared | 7/19/2024 | SUNMIN LEE |
| Grading Pre-Inspection | Cleared | 7/19/2024 | SUNMIN LEE |
| Hydrant and Access approval | Cleared | 7/22/2024 | KURT CORRAL |
| Senate Bill 9 | Cleared | 7/29/2024 | ASHLEY RODARTE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng D; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/5/2024 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 11/5/2024 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 11/20/2024 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 3/18/2025 | Approved | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 4/16/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/12/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/5/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 6/5/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 6/5/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 6/5/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 6/5/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 6/5/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 6/5/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/10/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 6/10/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 6/10/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 6/10/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 6/10/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/12/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 6/12/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 6/12/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 6/12/2025 | Approved | CHRISTOPHER ROJAS |
| Rough-Elec/Plmb/HVAC | 6/12/2025 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 6/12/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 6/16/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 6/23/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 8/27/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 8/27/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 8/27/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 8/27/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 8/27/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 8/27/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 8/27/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 8/27/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 9/11/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 9/11/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 9/11/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Final | 9/11/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 9/11/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 9/11/2025 | SGSOV Not Required | NICHOLAS TROWBRIDGE |
| Service/Power Release | 9/11/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 9/11/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 10/7/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 10/7/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 10/7/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Final | 10/7/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 10/7/2025 | Approved | NICHOLAS TROWBRIDGE |
| Service/Power Release | 10/7/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 11/3/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 11/3/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 11/3/2025 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 11/3/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 11/10/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 11/10/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 11/10/2025 | Approved | CHRISTOPHER ROJAS |