14658-14660 W RAYEN ST 91402

Certificate Information: 14658-14660 W RAYEN ST 91402

Application / Permit
23010-20000-04359
Plan Check / Job No.
B23VN14973
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan.: PROPOSED NEW 1200 SQ.FT 2 ADU'S PER STATE LOW, 600 SQ.FT EACH WITH 2 BEDROOMS, KITCHEN, DINING, LIVING AND BATHROOM.
Permit Issued
Issued on 1/31/2024
Issuing Office
Current Status
Issued on 1/31/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/1/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 RACHEL BEYENE
Corrections Issued 11/17/2023 RACHEL BEYENE
Quality Review Completed 11/21/2023 PRANITA SHAH
Applicant returned to address corrections 12/14/2023 RACHEL BEYENE
Applicant returned to address corrections 12/22/2023 RACHEL BEYENE
Applicant returned to address corrections 12/27/2023 RACHEL BEYENE
Plan Check Approved 1/26/2024 JAD BASMA
Issued 1/31/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/20/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 11/20/2023 NIKKI ZULUETA
Sewer availability Cleared 1/3/2024 ROSE MARIE SMITH
Low Impact Development (LID) Cleared 1/4/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 1/8/2024 COLIN LOREDO

Contact Information

Contractor New Beginning Construction Company Corp The; Lic. No.: 848904-B       ,
Contractor New Beginnning Construction Company The; Lic. No.: 848904-B       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 7/27/2026   
BUILDING-Rough-Frame 7/27/2026   
Smoke Detectors 7/27/2026   
Service/Power Release 7/27/2026   
SGSOV-Seismic Gas S/O Valve 7/27/2026   
Verify Sprinkler Sign Off 7/27/2026   

Inspection Request History

Footing/Foundation/Slab 3/15/2024 Corrections Issued CHRISTOPHER ROJAS
Underground Mechanical 3/15/2024 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 3/21/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 3/21/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/6/2024 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Corrections Issued KIRK SANDERS
PLUMBING-Rough 5/6/2024 Approved KIRK SANDERS
Deputy Wood Construction 5/8/2024 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 5/8/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/8/2024 Partial Approval KIRK SANDERS
HVAC-Rough 5/8/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 5/22/2024 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 5/22/2024 Partial Approval VINCENT HANLEY
Green Building Rough 5/22/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/22/2024 Partial Approval VINCENT HANLEY
Underground Mechanical 5/22/2024 Partial Approval VINCENT HANLEY
Insulation 6/7/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/7/2024 Partial Approval VINCENT HANLEY
Insulation 6/12/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/12/2024 Corrections Issued VINCENT HANLEY
Drywall Nailing 6/28/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/28/2024 Approved VINCENT HANLEY
Underground Mechanical 8/13/2025 No Access for Inspection JOSE AVILA
Service/Power Release 12/22/2025 Corrections Issued VINCENT HANLEY