9402 N ENCINO AVE 91325

Certificate Information: 9402 N ENCINO AVE 91325

Application / Permit
23010-20000-04358
Plan Check / Job No.
B23VN14970
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. New detached 2 story (31' x 44'8")ADU with attached garage per LAMC 12.22 A.33(c) AND (d) NFPA 13D Fire Sprinkler System is required.
Permit Issued
Issued on 10/9/2024
Issuing Office
Current Status
CofO Issued on 2/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 NGHI SU
Corrections Issued 11/20/2023 NGHI SU
Quality Review Completed 12/13/2023 YOUNG KIM
Applicant returned to address corrections 9/27/2024 NGHI SU
Plan Check Approved 10/3/2024 NGHI SU
Issued 10/9/2024 APPLICANT
CofO in Progress 1/22/2026 CHRISTOPHER ROJAS
Permit Finaled 2/3/2026 RUBEN SALAS
CofO Issued 2/3/2026 RUBEN SALAS
Permit Finaled 2/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/14/2024 CARLOS AGUILERA
Construction near power lines Cleared 4/1/2024 RIDWAN HARDY
Construction within easement Cleared 4/1/2024 RIDWAN HARDY
Hydrant and Access approval Cleared 6/20/2024 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 8/14/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 8/14/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 8/14/2024 CARLOS AGUILERA
Sewer availability Cleared 8/14/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/5/2024 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 12/20/2024 Partial Approval GAREN HAYRAPETYAN
Excavation/Setback/Form/Re-Bar 12/30/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 12/30/2024 Approved JAVIER RAMOS JR
Special/Order Compliance 12/30/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 1/29/2025 Partial Inspection JAVIER RAMOS JR
Verify Sprinkler Sign Off 1/29/2025 Corrections Issued JAVIER RAMOS JR
Deputy Wood Construction 1/30/2025 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 2/20/2025 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/20/2025 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 3/11/2025 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 3/18/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 3/18/2025 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 3/18/2025 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 3/18/2025 Approved JAVIER RAMOS JR
Insulation 4/11/2025 Corrections Issued NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 4/16/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/16/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 4/16/2025 Approved CHRISTOPHER ROJAS
Insulation 4/16/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 4/25/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 5/15/2025 Approved LOUIS ESCOTO
Shower Pan 5/15/2025 Approved LOUIS ESCOTO
Sewer 5/30/2025 Approved CHRISTOPHE COCHRAN
Underground Mechanical 6/12/2025 Partial Approval NICHOLAS TROWBRIDGE
ELECTRICAL-Final 9/4/2025 Corrections Issued NICHOLAS TROWBRIDGE
HVAC-Final 9/4/2025 Corrections Issued NICHOLAS TROWBRIDGE
PLUMBING-Final 9/4/2025 Corrections Issued NICHOLAS TROWBRIDGE
ELECTRICAL-Final 9/18/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 9/18/2025 Corrections Issued NICHOLAS TROWBRIDGE
PLUMBING-Final 9/18/2025 Approved NICHOLAS TROWBRIDGE
Final 10/2/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 10/2/2025 Approved NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 10/2/2025 SGSOV Not Required NICHOLAS TROWBRIDGE
Service/Power Release 10/2/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Smoke Detectors 10/2/2025 Approved NICHOLAS TROWBRIDGE
Final 1/22/2026 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 1/22/2026 Approved CHRISTOPHER ROJAS