16712 W TUBA ST 91343
Certificate Information: 16712 W TUBA ST 91343
- Application / Permit
- 23010-20000-04342
- Plan Check / Job No.
- B23VN14909
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 2/9/2024
- Issuing Office
- Current Status
- CofO Issued on 4/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | DANIEL YIP |
| Corrections Issued | 11/12/2023 | DANIEL YIP |
| Quality Review Completed | 11/14/2023 | GARO TELMI |
| Plan Check Approved | 2/6/2024 | DANIEL YIP |
| Issued | 2/9/2024 | APPLICANT |
| CofO in Progress | 4/23/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 4/25/2025 | RUBEN SALAS |
| CofO Issued | 4/25/2025 | RUBEN SALAS |
| Permit Finaled | 4/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/27/2023 | RIDWAN HARDY |
| Address approval | Cleared | 1/4/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/4/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 1/29/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 1/30/2024 | EDGAR ALCARAZ |
| GPI Written Notices | Cleared | 2/6/2024 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 2/6/2024 | DANIEL YIP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 450 NORTH BRAND BLVD STE 600 GLENDALE, CA 91203 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/12/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/12/2024 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/21/2024 | Partial Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2024 | Corrections Issued | JOHN COLEMAN |
| Green Building Rough | 5/21/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 5/21/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 6/17/2024 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/17/2024 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 6/17/2024 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/17/2024 | Corrections Issued | JAVIER RAMOS JR |
| Sewer | 6/17/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 6/17/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/26/2024 | Partial Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 6/26/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 6/26/2024 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/26/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/26/2024 | Approved | JAVIER RAMOS JR |
| Shower Pan | 6/26/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 7/2/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 7/2/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/6/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 12/6/2024 | Approved | JAVIER RAMOS JR |
| Final | 12/6/2024 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 12/6/2024 | No Access for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 12/6/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 12/6/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 12/6/2024 | SGSOV Not Required | JAVIER RAMOS JR |
| Smoke Detectors | 12/6/2024 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 12/10/2024 | Corrections Issued | JAVIER RAMOS JR |
| Final | 1/29/2025 | Corrections Issued | JAVIER RAMOS JR |
| Final | 4/21/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 4/21/2025 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 4/21/2025 | Approved | CHRISTOPHER ROJAS |