16712 W TUBA ST 91343

Certificate Information: 16712 W TUBA ST 91343

Application / Permit
23010-20000-04342
Plan Check / Job No.
B23VN14909
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 2/9/2024
Issuing Office
Current Status
CofO Issued on 4/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 DANIEL YIP
Corrections Issued 11/12/2023 DANIEL YIP
Quality Review Completed 11/14/2023 GARO TELMI
Plan Check Approved 2/6/2024 DANIEL YIP
Issued 2/9/2024 APPLICANT
CofO in Progress 4/23/2025 CHRISTOPHER ROJAS
Permit Finaled 4/25/2025 RUBEN SALAS
CofO Issued 4/25/2025 RUBEN SALAS
Permit Finaled 4/25/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 12/27/2023 RIDWAN HARDY
Address approval Cleared 1/4/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/4/2024 EDGAR ALCARAZ
Sewer availability Cleared 1/4/2024 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 1/29/2024 LUIS CRUZ
Roof/Waste drainage to street Cleared 1/30/2024 EDGAR ALCARAZ
GPI Written Notices Cleared 2/6/2024 DANIEL YIP
Grading Pre-Inspection Cleared 2/6/2024 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 450 NORTH BRAND BLVD STE 600      GLENDALE, CA 91203

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/12/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 4/12/2024 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/8/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 5/21/2024 Partial Approval JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Corrections Issued JOHN COLEMAN
Green Building Rough 5/21/2024 Not Ready for Inspection JOHN COLEMAN
Verify Sprinkler Sign Off 5/21/2024 Approved JOHN COLEMAN
BUILDING-Rough-Frame 6/17/2024 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 6/17/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/17/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 6/17/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 6/17/2024 Corrections Issued JAVIER RAMOS JR
Sewer 6/17/2024 Approved JAVIER RAMOS JR
Underground Mechanical 6/17/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 6/26/2024 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/26/2024 Approved JAVIER RAMOS JR
HVAC-Rough 6/26/2024 Approved JAVIER RAMOS JR
Insulation 6/26/2024 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 6/26/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 6/26/2024 Approved JAVIER RAMOS JR
Shower Pan 6/26/2024 Approved JAVIER RAMOS JR
Drywall Nailing 7/2/2024 Approved JENNIFER RABUCHIN
Green Building Rough 7/2/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/6/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 12/6/2024 Approved JAVIER RAMOS JR
Final 12/6/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 12/6/2024 No Access for Inspection JAVIER RAMOS JR
HVAC-Final 12/6/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 12/6/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/6/2024 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 12/6/2024 Approved JAVIER RAMOS JR
Pre-Inspection 12/10/2024 Corrections Issued JAVIER RAMOS JR
Final 1/29/2025 Corrections Issued JAVIER RAMOS JR
Final 4/21/2025 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 4/21/2025 Approved CHRISTOPHER ROJAS
Service/Power Release 4/21/2025 Approved CHRISTOPHER ROJAS