13639 W VICTORY BLVD M 91401

Certificate Information: 13639 W VICTORY BLVD M 91401

Application / Permit
23010-20000-04330
Plan Check / Job No.
B23VN14856
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(18) School - private
Work Description
eplan: BLDG "M" (N) 40' X 24' MODULAR CLASSROOM BUILDING PER HCD APPROVAL AND ENGINEERING- NFPA 13 REQUIRED THROUGHOUT PER CPC-2023-5228-VCU
Permit Issued
Issued on 7/30/2024
Issuing Office
Current Status
CofO Issued on 4/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 SEWADA ZADOORIAN MILAGARDI
Assigned to Zoning Architect 11/17/2023 SARHAD GHEVANDIAN
Corrections Issued 11/22/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 11/30/2023 STEVEN KIM
Applicant returned to address corrections 2/27/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 3/4/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 3/26/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 5/30/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 6/4/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 6/13/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 7/30/2024 SEWADA ZADOORAN MILAGARDI
Issued 7/30/2024 APPLICANT
CofO in Progress 4/22/2025 JOHN KITCKO
Permit Finaled 4/28/2025 RICKEY JACKSON
CofO Issued 4/28/2025 RICKEY JACKSON
Permit Finaled 4/28/2025 RICKEY JACKSON

Permit Application Clearance Information

DAS Clearance Cleared 2/29/2024 Pinank Patel
Eng Process Fee Ord 176,300 Cleared 3/7/2024 CARLOS RAMIREZ
Construction near power lines Cleared 3/14/2024 EDGAR PASCUA
Green Code Cleared 3/24/2024 Pinank Patel
Address approval Cleared 4/1/2024 CARLOS RAMIREZ
Hydrant and Access approval Cleared 4/23/2024 JOHN CONNEALLY
Sewer availability Cleared 5/3/2024 LEE GUILBEAUX
Low Impact Development (LID) Cleared 5/10/2024 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 5/13/2024 LEE GUILBEAUX
Fire Marshal Fire Life Safety Cleared 5/30/2024 RONILO MULAWIN
"Q" conditions Cleared 7/23/2024 CLAUDE GOODING
CPC Cleared 7/23/2024 CLAUDE GOODING
Tract Map conditions Cleared 7/23/2024 CLAUDE GOODING
ZA Case Cleared 7/23/2024 CLAUDE GOODING
ZA Case Cleared 7/23/2024 CLAUDE GOODING
Zoning Plan Check Cleared 7/25/2024 SARHAD GHEVANDIAN

Contact Information

Architect Masotta,, John Joseph; Lic. No.: C24805 391 S BURNSIDE AVE      LOS ANGELES, CA 90036
Contractor Del Amo Construction Llc; Lic. No.: 744458-B       ,
Engineer Dermendjian,, Raffi Hrag; Lic. No.: C88261 9325 SHOSHONE AVENUE      NORTHRIDGE, CA 91325
Engineer Gavazza,, Jeffrey Bryan; Lic. No.: C59894 472 35TH ST      MANHATTAN BEACH, CA 90266

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/28/2024 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 9/5/2024 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 9/25/2024 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 10/7/2024 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 12/5/2024 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 12/5/2024 Partial Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 12/13/2024 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 12/26/2024 Partial Approval JOHN KITCKO
Drywall Nailing 4/21/2025 Approved JOHN KITCKO
Final 4/21/2025 OK to Issue CofO JOHN KITCKO
Footing/Foundation/Slab 4/21/2025 Approved JOHN KITCKO
Green Building Final 4/21/2025 Approved JOHN KITCKO
Green Building Rough 4/21/2025 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 4/21/2025 SGSOV Approved JOHN KITCKO
Smoke Detectors 4/21/2025 Approved JOHN KITCKO
Verify Sprinkler Sign Off 4/21/2025 Approved JOHN KITCKO
Wood Frame 4/21/2025 Approved JOHN KITCKO
Special/Order Compliance 4/22/2025 Partial Inspection JOHN KITCKO