13639 W VICTORY BLVD M 91401
Certificate Information: 13639 W VICTORY BLVD M 91401
- Application / Permit
- 23010-20000-04330
- Plan Check / Job No.
- B23VN14856
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (18) School - private
- Work Description
- eplan: BLDG "M" (N) 40' X 24' MODULAR CLASSROOM BUILDING PER HCD APPROVAL AND ENGINEERING- NFPA 13 REQUIRED THROUGHOUT PER CPC-2023-5228-VCU
- Permit Issued
- Issued on 7/30/2024
- Issuing Office
- Current Status
- CofO Issued on 4/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | SEWADA ZADOORIAN MILAGARDI |
| Assigned to Zoning Architect | 11/17/2023 | SARHAD GHEVANDIAN |
| Corrections Issued | 11/22/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 11/30/2023 | STEVEN KIM |
| Applicant returned to address corrections | 2/27/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 3/4/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 3/26/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 5/30/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 6/4/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 6/13/2024 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 7/30/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 7/30/2024 | APPLICANT |
| CofO in Progress | 4/22/2025 | JOHN KITCKO |
| Permit Finaled | 4/28/2025 | RICKEY JACKSON |
| CofO Issued | 4/28/2025 | RICKEY JACKSON |
| Permit Finaled | 4/28/2025 | RICKEY JACKSON |
Permit Application Clearance Information
| DAS Clearance | Cleared | 2/29/2024 | Pinank Patel |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2024 | CARLOS RAMIREZ |
| Construction near power lines | Cleared | 3/14/2024 | EDGAR PASCUA |
| Green Code | Cleared | 3/24/2024 | Pinank Patel |
| Address approval | Cleared | 4/1/2024 | CARLOS RAMIREZ |
| Hydrant and Access approval | Cleared | 4/23/2024 | JOHN CONNEALLY |
| Sewer availability | Cleared | 5/3/2024 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 5/10/2024 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 5/13/2024 | LEE GUILBEAUX |
| Fire Marshal Fire Life Safety | Cleared | 5/30/2024 | RONILO MULAWIN |
| "Q" conditions | Cleared | 7/23/2024 | CLAUDE GOODING |
| CPC | Cleared | 7/23/2024 | CLAUDE GOODING |
| Tract Map conditions | Cleared | 7/23/2024 | CLAUDE GOODING |
| ZA Case | Cleared | 7/23/2024 | CLAUDE GOODING |
| ZA Case | Cleared | 7/23/2024 | CLAUDE GOODING |
| Zoning Plan Check | Cleared | 7/25/2024 | SARHAD GHEVANDIAN |
Contact Information
| Architect | Masotta,, John Joseph; Lic. No.: C24805 | 391 S BURNSIDE AVE LOS ANGELES, CA 90036 |
| Contractor | Del Amo Construction Llc; Lic. No.: 744458-B | , |
| Engineer | Dermendjian,, Raffi Hrag; Lic. No.: C88261 | 9325 SHOSHONE AVENUE NORTHRIDGE, CA 91325 |
| Engineer | Gavazza,, Jeffrey Bryan; Lic. No.: C59894 | 472 35TH ST MANHATTAN BEACH, CA 90266 |
Inspector Information
| DEANDRE HOFFMAN, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/28/2024 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 9/5/2024 | Partial Approval | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 9/25/2024 | Partial Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 10/7/2024 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 12/5/2024 | Partial Approval | DANNY RODRIGUEZ |
| Reinforced Concrete Frame | 12/5/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 12/13/2024 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 12/26/2024 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 4/21/2025 | Approved | JOHN KITCKO |
| Final | 4/21/2025 | OK to Issue CofO | JOHN KITCKO |
| Footing/Foundation/Slab | 4/21/2025 | Approved | JOHN KITCKO |
| Green Building Final | 4/21/2025 | Approved | JOHN KITCKO |
| Green Building Rough | 4/21/2025 | Approved | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Approved | JOHN KITCKO |
| Smoke Detectors | 4/21/2025 | Approved | JOHN KITCKO |
| Verify Sprinkler Sign Off | 4/21/2025 | Approved | JOHN KITCKO |
| Wood Frame | 4/21/2025 | Approved | JOHN KITCKO |
| Special/Order Compliance | 4/22/2025 | Partial Inspection | JOHN KITCKO |