9964 N VENA AVE 91331
Certificate Information: 9964 N VENA AVE 91331
- Application / Permit
- 23010-20000-04325
- Plan Check / Job No.
- B23VN14846
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22'-0" X 40'-0" DETACHED ACCESSORY DWELLING UNIT WITH 2' X 5' ATTACHED COVERED PORCH PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 1/25/2024
- Issuing Office
- Current Status
- CofO Issued on 10/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 11/4/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 11/16/2023 | APPLICANT |
| Applicant returned to address corrections | 1/25/2024 | MADISON ODELL |
| Issued | 1/25/2024 | APPLICANT |
| CofO in Progress | 9/20/2024 | MICHEL ABAJAN |
| Permit Finaled | 10/9/2024 | DANIEL ORRANTE |
| CofO Issued | 10/9/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/9/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/21/2023 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2023 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 12/12/2023 | CARLOS RAMIREZ |
| Low Impact Development (LID) | Cleared | 1/23/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 1/25/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 2/27/2024 | Approved | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 3/11/2024 | Conditional Approval | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 3/11/2024 | Conditional Approval | KEVIN BERBERYAN |
| METHANE-Barrier | 3/11/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| METHANE-Subgrade | 3/11/2024 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 3/18/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2024 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 3/29/2024 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2024 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/19/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/19/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 4/19/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 4/19/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/19/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 4/19/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/19/2024 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 4/19/2024 | Approved | MICHEL ABAJAN |
| Insulation | 4/23/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 4/26/2024 | Approved | LEONARD ROSS II |
| Interior/Exterior Lathing | 5/14/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 5/14/2024 | Approved | MICHEL ABAJAN |
| Final | 9/12/2024 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 9/12/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 9/12/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 9/12/2024 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 9/12/2024 | Approved | MICHEL ABAJAN |