4519 N BEN AVE 91607

Certificate Information: 4519 N BEN AVE 91607

Application / Permit
23010-20000-04324
Plan Check / Job No.
B23VN14837
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 61' X 62'-5" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 4/22/2024
Issuing Office
West Los Angeles
Current Status
Issued on 4/22/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/27/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 SELLA BENYAMIN
Corrections Issued 11/14/2023 SELLA BENYAMIN
Quality Review Completed 11/16/2023 STEVEN KIM
Quality Review Completed 11/16/2023 STEVEN KIM
Building Plans Picked Up 11/21/2023 APPLICANT
Applicant returned to address corrections 12/12/2023 SELLA BENYAMIN
Plan Check Approved 4/2/2024 SELLA BENYAMIN
Issued 4/22/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/13/2023 EDGAR ALCARAZ
ZI Cleared 1/4/2024 JAZMIN ROQUE
Trees in Parkway Cleared 1/24/2024 ADALBERTO VERA
Hydrant and Access approval Cleared 1/26/2024 JOHN CONNEALLY
Low Impact Development (LID) Cleared 2/26/2024 ERNEST TSE
Sewer availability Cleared 3/5/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 3/12/2024 EDGAR ALCARAZ
Permit Cleared 3/15/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Karapetian,, Arbi; Lic. No.: C79953 6854 FOOTHILL BLVD      TUJUNGA, CA 91042

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/26/2024 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Pre-Inspection 4/29/2024 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 6/25/2024 Partial Approval CHRISTOPHER ROJAS
Deputy Reinf. Concrete 7/2/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 7/2/2024 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/2/2024 Approved CHRISTOPHER ROJAS
Deputy Reinf. Concrete 7/8/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/14/2024 Partial Approval CHRISTOPHER ROJAS
Deputy Wood Construction 9/3/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 9/6/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 9/26/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 12/10/2024 Partial Approval CHRISTOPHER ROJAS
Sewer 12/10/2024 Partial Approval CHRISTOPHER ROJAS
HVAC-Rough 2/3/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 2/3/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/4/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 2/28/2025 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 3/18/2025 Approved CHRISTOPHER ROJAS
Pre-Inspection 3/26/2025 Approved JAVIER RAMOS JR
HVAC-Rough 4/2/2025 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 4/7/2025 Partial Approval JAVIER RAMOS JR
Green Building Rough 4/7/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 4/7/2025 Partial Approval JAVIER RAMOS JR
Underground Mechanical 4/7/2025 Partial Inspection JAVIER RAMOS JR
Verify Sprinkler Sign Off 4/7/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 4/15/2025 Approved JAVIER RAMOS JR
Insulation 4/15/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 4/15/2025 Approved JAVIER RAMOS JR
MERV13>=Rough 4/15/2025 Approved JAVIER RAMOS JR
Shower Pan 4/21/2025 Approved JAVIER RAMOS JR
Drywall Nailing 5/19/2025 Approved JAVIER RAMOS JR