9758-9760 N HASKELL AVE 91343

Certificate Information: 9758-9760 N HASKELL AVE 91343

Application / Permit
23010-20000-04315
Plan Check / Job No.
B23VN14812
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*eplan* BUILD NEW CONSTRUCTION 1ST FLOOR SB9 (1,292 S.F.) AND 2ND FLOOR ADU (800 S.F.) ADU CHECKED PER LAMC 12.22 A.33 (C)-(D) SB9 CHECKED WITH 2 UNIT DEVELOPMENT CA GOVT CODE 65852.21
Permit Issued
Issued on 12/4/2024
Issuing Office
Current Status
Issued on 12/4/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/27/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 SUNMIN LEE
Corrections Issued 11/16/2023 SUNMIN LEE
Quality Review Completed 11/17/2023 GARO TELMI
Applicant returned to address corrections 5/13/2024 SUNMIN LEE
Applicant returned to address corrections 8/9/2024 SUNMIN LEE
Applicant returned to address corrections 9/17/2024 SUNMIN LEE
Applicant returned to address corrections 10/8/2024 SUNMIN LEE
Plan Check Approved 11/1/2024 SUNMIN LEE
Plan Check Approved 12/4/2024 SUNMIN LEE
Issued 12/4/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/18/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/19/2023 CARLOS AGUILERA
Sewer availability Cleared 12/19/2023 CARLOS AGUILERA
Senate Bill 9 Cleared 12/21/2023 NELSON RODRIGUEZ
Hydrant and Access approval Cleared 2/5/2024 KURT CORRAL
Low Impact Development (LID) Cleared 3/21/2024 LUIS CRUZ
Roof/Waste drainage to street Cleared 4/9/2024 CARLOS AGUILERA
Demolition Cleared 8/15/2024 BRENNEN OBETO

Contact Information

Contractor Owner-Builder       ,
Engineer Keshishian,, Vahram; Lic. No.: S6482 1102 SAN RAFAEL AVE      GLENDALE, CA 91202

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/11/2025 Corrections Issued GAREN HAYRAPETYAN
Special/Order Compliance 2/11/2025 Corrections Issued GAREN HAYRAPETYAN
Special/Order Compliance 2/11/2025 Partial Inspection RAUL OLAGI
Footing/Foundation/Slab 5/2/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 6/11/2025 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/11/2025 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/31/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 11/6/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 11/6/2025 Approved GAREN HAYRAPETYAN
MERV13>=Rough 11/6/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 11/6/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 12/10/2025 Partial Approval GAREN HAYRAPETYAN
MERV13>=Rough 12/10/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 12/10/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 12/10/2025 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 1/15/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Interior/Exterior Lathing 1/15/2026 Partial Approval GAREN HAYRAPETYAN
Sewer 1/15/2026 Approved GAREN HAYRAPETYAN
Shower Pan 1/15/2026 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 1/21/2026 Partial Approval JENNIFER RABUCHIN
Insulation 1/21/2026 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 1/21/2026 Approved JENNIFER RABUCHIN
Drywall Nailing 2/5/2026 Approved MICHEL ABAJAN
Underground Mechanical 2/5/2026 Approved MICHEL ABAJAN