6214 N SATSUMA AVE 91606

Certificate Information: 6214 N SATSUMA AVE 91606

Application / Permit
23010-20000-04299
Plan Check / Job No.
B23VN14750
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 10/10/2024
Issuing Office
Current Status
Issued on 10/10/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/27/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 DANIEL YIP
Corrections Issued 11/16/2023 DANIEL YIP
Quality Review Completed 11/16/2023 GARO TELMI
Applicant returned to address corrections 9/17/2024 DANIEL YIP
Plan Check Approved 10/9/2024 DANIEL YIP
Issued 10/10/2024 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 3/8/2024 RIDWAN HARDY
Address approval Cleared 4/17/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/6/2024 BIAINA HARITUNIAN
Sewer availability Cleared 5/6/2024 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 7/24/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/26/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/19/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 11/19/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 12/4/2025 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 12/4/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 12/4/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Corrections Issued JOSE AVILA
Deputy Wood Construction 12/18/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/30/2025 Corrections Issued JOSE AVILA
Special/Order Compliance 1/15/2026 Partial Inspection JOSE AVILA
Underground Mechanical 3/5/2026 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/25/2026 Approved GAREN HAYRAPETYAN
Wood Frame 3/25/2026 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 4/6/2026 Approved GAREN HAYRAPETYAN
HVAC-Rough 4/6/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 4/6/2026 Partial Approval GAREN HAYRAPETYAN
PLUMBING-Rough 4/6/2026 Approved GAREN HAYRAPETYAN
Insulation 4/9/2026 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 4/15/2026 Approved GAREN HAYRAPETYAN
Green Building Rough 4/15/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 5/5/2026 Approved GAREN HAYRAPETYAN
Shower Pan 5/5/2026 Approved GAREN HAYRAPETYAN