16044 W LEADWELL ST 91406
Certificate Information: 16044 W LEADWELL ST 91406
- Application / Permit
- 23010-20000-04275
- Plan Check / Job No.
- B23VN12932
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan 2- NEW 34' X 21' IRREGULAR SHAPED TWO STORY DETACHED ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33 (C) AND (D), NFPA-13R FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING - SEE COMMENTS
- Permit Issued
- Issued on 3/20/2024
- Issuing Office
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2023 | RARES BODEA |
| Corrections Issued | 10/26/2023 | RARES BODEA |
| Quality Review Completed | 10/27/2023 | STEVEN KIM |
| Applicant returned to address corrections | 2/29/2024 | RARES BODEA |
| Applicant returned to address corrections | 3/12/2024 | RARES BODEA |
| Applicant returned to address corrections | 3/14/2024 | RARES BODEA |
| Plan Check Approved | 3/15/2024 | RARES BODEA |
| Issued | 3/20/2024 | APPLICANT |
| CofO in Progress | 9/2/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
| CofO Issued | 9/9/2025 | RUBEN SALAS |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/15/2023 | NIKKI ZULUETA |
| "Q" conditions | Cleared | 12/18/2023 | NELSON RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2023 | NIKKI ZULUETA |
| Tract Map conditions | Cleared | 12/18/2023 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 12/18/2023 | NELSON RODRIGUEZ |
| ZI | Cleared | 12/18/2023 | NELSON RODRIGUEZ |
| Permit | Cleared | 12/20/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 12/20/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 1/24/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 2/6/2024 | COLIN LOREDO |
| Trees in Parkway | Cleared | 2/6/2024 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 2/15/2024 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 3876 HUNTERS GROVE CT MOORPARK, CA 93021 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/22/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 4/22/2024 | Partial Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 4/25/2024 | Not Ready for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 4/25/2024 | Corrections Issued | RAUL OLAGI |
| Grounding or Bonding | 4/25/2024 | Not Ready for Inspection | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 4/26/2024 | Approved | KEVIN BERBERYAN |
| Deputy Steel/Welding | 5/15/2024 | Conditional Approval | JUAN VALENZUELA |
| Sewer | 5/15/2024 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2024 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 6/21/2024 | Approved | RAUL OLAGI |
| HVAC-Rough | 6/21/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 6/21/2024 | Corrections Issued | RAUL OLAGI |
| Deputy Wood Construction | 6/24/2024 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/25/2024 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2024 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 6/25/2024 | Partial Approval | RAUL OLAGI |
| Verify Sprinkler Sign Off | 6/25/2024 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/28/2024 | Approved | RAUL OLAGI |
| HVAC-Rough | 6/28/2024 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 6/28/2024 | Approved | RAUL OLAGI |
| Sewer | 6/28/2024 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 6/28/2024 | Approved | RAUL OLAGI |
| Insulation | 7/10/2024 | Approved | RAUL OLAGI |
| Underground Mechanical | 7/10/2024 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 7/16/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 7/16/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 7/16/2024 | Partial Approval | RAUL OLAGI |
| Shower Pan | 8/1/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 8/12/2024 | Approved | RAUL OLAGI |
| Underground Mechanical | 1/10/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 1/15/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 6/12/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 6/12/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 6/12/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Final | 6/12/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Final | 6/12/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 6/12/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV No Gas | SALVADOR MARTINEZ |
| Service/Power Release | 6/12/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 6/12/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 7/18/2025 | Approved | SALVADOR MARTINEZ |
| Final | 7/18/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 7/18/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Final | 7/18/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Final | 7/18/2025 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 7/18/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 7/18/2025 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 7/28/2025 | Approved | SALVADOR MARTINEZ |
| Final | 8/18/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 8/18/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 8/21/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 8/21/2025 | Approved | SALVADOR MARTINEZ |
| Final | 9/2/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |