1177 W 29TH ST 90007
Certificate Information: 1177 W 29TH ST 90007
- Application / Permit
- 23010-20000-04266
- Plan Check / Job No.
- B23VN14630
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached 43' x 31' 6" irregular shaped two story ADU per LAMC 12.22 A.33 (c)-(d). All work done per engineer.
- Permit Issued
- Issued on 2/14/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2023 | NAREG ATARIAN |
| Corrections Issued | 10/28/2023 | NAREG ATARIAN |
| Quality Review Completed | 10/31/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 11/3/2023 | APPLICANT |
| Plan Check Approved | 2/12/2024 | NAREG ATARIAN |
| Issued | 2/14/2024 | APPLICANT |
| CofO in Progress | 10/10/2025 | WILLIAM SIERRA |
| Permit Finaled | 10/11/2025 | DEROLD HAUFF |
| CofO Issued | 10/11/2025 | DEROLD HAUFF |
| Permit Finaled | 10/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/31/2023 | JEANIE LAM |
| Miscellaneous | Cleared | 10/31/2023 | JASON CHAN |
| ZA Case | Cleared | 10/31/2023 | JASON CHAN |
| ZI | Cleared | 10/31/2023 | JASON CHAN |
| Hydrant and Access approval | Cleared | 11/16/2023 | LAVEON RIDER |
| HPOZ | Cleared | 1/9/2024 | DANIEL MATA |
| ZI | Cleared | 1/9/2024 | DANIEL MATA |
| Construction near power lines | Cleared | 1/19/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 2/2/2024 | MELINEH AGHAKHABIAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2024 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 2/3/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 2/3/2024 | ADRIAN SANCHEZ |
Contact Information
| Architect | Nigosian,, Michael Nickolas; Lic. No.: C35308 | 75-572 PAINTED DESERT DRIVE INDIAN WELLS, CA 92210 |
| Contractor | Owner-Builder | , |
| Engineer | Boranian,, Paul; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 2/27/2024 | Partial Approval | ARTHUR NEGRETE |
| Special/Order Compliance | 2/27/2024 | Corrections Issued | ARTHUR NEGRETE |
| Underground Mechanical | 2/27/2024 | Partial Approval | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 3/4/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Barrier | 3/4/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Subgrade | 3/4/2024 | Approved | ARTHUR NEGRETE |
| Wood Frame | 3/14/2024 | Approved | ARTHUR NEGRETE |
| Deputy Wood Construction | 3/15/2024 | Approved | ARTHUR NEGRETE |
| Wood Frame | 4/3/2024 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 5/2/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 5/2/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 5/2/2024 | Approved | ARTHUR NEGRETE |
| Insulation | 5/22/2024 | Not Ready for Inspection | JOSH MEISTER |
| BUILDING-Rough-Frame | 5/28/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 5/28/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 5/28/2024 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 5/28/2024 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 5/28/2024 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 5/28/2024 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 6/10/2024 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 6/10/2024 | Partial Inspection | WILLIAM KUEHN |
| Interior/Exterior Lathing | 6/13/2024 | Partial Inspection | WILLIAM KUEHN |
| Shower Pan | 7/24/2024 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 7/26/2024 | Partial Approval | WILLIAM SIERRA |
| Final | 6/10/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 6/10/2025 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 6/10/2025 | SGSOV Approved | WILLIAM SIERRA |
| Service/Power Release | 6/10/2025 | Not Required | WILLIAM SIERRA |
| Smoke Detectors | 6/10/2025 | Approved | WILLIAM SIERRA |
| Final | 6/16/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 6/16/2025 | Approved | WILLIAM SIERRA |
| Final | 10/8/2025 | OK to Issue CofO | WILLIAM SIERRA |