6637 N BERQUIST AVE 91307
Certificate Information: 6637 N BERQUIST AVE 91307
- Application / Permit
- 23010-20000-04264
- Plan Check / Job No.
- B23VN14612
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 17'-6" X 31' ONE-STORY DETACHED, FULLY ELECTRIC ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22.A.33(c),(d), AND (g). WORK PER WFPP.
- Permit Issued
- Issued on 1/28/2025
- Issuing Office
- Current Status
- CofO Issued on 4/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2023 | MADISON ODELL |
| Corrections Issued | 10/27/2023 | MADISON ODELL |
| Applicant returned to address corrections | 2/21/2024 | MADISON ODELL |
| Plan Check Approved | 2/24/2024 | ANGELICA MARTINEZ |
| Issued | 1/28/2025 | APPLICANT |
| CofO in Progress | 2/2/2026 | TROY SANDERS |
| Permit Finaled | 4/4/2026 | MICHAEL PELHAM |
| CofO Issued | 4/4/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/4/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 11/3/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2023 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 12/21/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 12/21/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/9/2024 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 2/10/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/24/2025 | Not Ready for Inspection | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 4/29/2025 | Corrections Issued | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 4/29/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Underground Mechanical | 4/29/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 5/2/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Underground Mechanical | 5/2/2025 | Approved | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/6/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/8/2025 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Partial Approval | GEVORK IPCHYAN |
| Green Building Rough | 5/28/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Verify Sprinkler Sign Off | 5/28/2025 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2025 | Partial Approval | GEVORK IPCHYAN |
| Green Building Rough | 6/16/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 6/18/2025 | Partial Approval | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 7/21/2025 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 7/21/2025 | Approved | TROY SANDERS |
| Green Building Rough | 7/21/2025 | Approved | TROY SANDERS |
| HVAC-Rough | 7/21/2025 | Approved | TROY SANDERS |
| PLUMBING-Rough | 7/21/2025 | Approved | TROY SANDERS |
| Insulation | 7/22/2025 | Approved | TROY SANDERS |
| Drywall Nailing | 7/24/2025 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 7/30/2025 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 8/14/2025 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Final | 8/14/2025 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Final | 8/14/2025 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Final | 9/24/2025 | Approved | TROY SANDERS |
| Final | 9/24/2025 | Corrections Issued | TROY SANDERS |
| HVAC-Final | 9/24/2025 | Approved | TROY SANDERS |
| PLUMBING-Final | 9/24/2025 | Approved | TROY SANDERS |
| Service/Power Release | 9/24/2025 | Approved | TROY SANDERS |
| HVAC-Final | 10/10/2025 | Approved | TROY SANDERS |
| PLUMBING-Final | 10/10/2025 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 1/30/2026 | Approved | TROY SANDERS |
| Final | 1/30/2026 | OK to Issue CofO | TROY SANDERS |
| Footing/Foundation/Slab | 1/30/2026 | Approved | TROY SANDERS |
| Green Building Final | 1/30/2026 | Approved | TROY SANDERS |
| PLUMBING-Final | 1/30/2026 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 1/30/2026 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 1/30/2026 | Approved | TROY SANDERS |