14934 W CHATSWORTH DR 91345

Certificate Information: 14934 W CHATSWORTH DR 91345

Application / Permit
23010-20000-04263
Plan Check / Job No.
B23VN14611
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New detached ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c),(d) and (g). Design per licensed engineer.
Permit Issued
Issued on 3/23/2024
Issuing Office
Current Status
Issued on 3/23/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/24/2023 APPLICANT
Assigned to Plan Check Engineer 10/27/2023 CAROLEAN BASMA
Corrections Issued 10/27/2023 CAROLEAN BASMA
Plan Check Approved 3/21/2024 CAROLEAN BASMA
Issued 3/23/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/30/2023 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 10/30/2023 BRYAN GODINEZ
Sewer availability Cleared 10/30/2023 BRYAN GODINEZ
Construction near power lines Cleared 2/10/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 3/5/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 3/5/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Xi,, Wang; Lic. No.: C85148 422 FALLINGSTAR      IRVINE, CA 92614
Engineer Xi,, Wang; Lic. No.: NA85148       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/22/2024 Partial Inspection JOHN COLEMAN
Sewer 6/14/2024 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 7/3/2024 Partial Inspection JENNIFER RABUCHIN
PLUMBING-Rough 7/3/2024 Partial Approval JENNIFER RABUCHIN
Sewer 7/3/2024 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 7/23/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/9/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/9/2024 Partial Approval JENNIFER RABUCHIN
Green Building Rough 8/9/2024 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 8/9/2024 Not Ready for Inspection JENNIFER RABUCHIN
Verify Sprinkler Sign Off 8/9/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/12/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 2/12/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 2/12/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 2/12/2025 Approved CHRISTOPHER ROJAS
MERV13>=Rough 2/12/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 2/12/2025 Approved CHRISTOPHER ROJAS
Insulation 3/6/2025 Conditional Approval MICHEL ABAJAN
Interior/Exterior Lathing 3/6/2025 Approved MICHEL ABAJAN
Drywall Nailing 3/11/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 7/15/2025 Approved JENNIFER RABUCHIN
Shower Pan 7/15/2025 Approved JENNIFER RABUCHIN
Final 7/14/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 7/14/2026 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 7/14/2026 Not Ready for Inspection JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/14/2026 SGSOV Not Required JENNIFER RABUCHIN
Service/Power Release 7/14/2026 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 7/14/2026 Not Ready for Inspection JENNIFER RABUCHIN