140 1/2 E 47TH PL 90011

Certificate Information: 140 1/2 E 47TH PL 90011

Application / Permit
23010-20000-04202
Plan Check / Job No.
B23VN14386
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32'x 37' DETACHED, IRREGULARLY SHAPED ACESSORY DWELLING UNIT (1099 SF) PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER WFPP.
Permit Issued
Issued on 2/14/2024
Issuing Office
Current Status
CofO Issued on 10/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2023 APPLICANT
Assigned to Plan Check Engineer 10/23/2023 MIROOSH KHACHATOORIAN
Corrections Issued 10/24/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 12/22/2023 MADISON ODELL
Applicant returned to address corrections 1/5/2024 MADISON ODELL
Applicant returned to address corrections 1/10/2024 MADISON ODELL
Plan Check Approved 2/13/2024 ALEC MOUSAKHANIAN
Issued 2/14/2024 APPLICANT
CofO in Progress 10/1/2024 ALEJANDRO DE ARTOLA
CofO Issued 10/15/2024 RUBEN SALAS
Permit Finaled 10/15/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/6/2023 JUSTIN BICOL
Low Impact Development (LID) Cleared 12/6/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 12/6/2023 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 12/12/2023 JUSTIN BICOL
Sewer availability Cleared 12/12/2023 JUSTIN BICOL
Tenant Habitability Plan Cleared 12/13/2023 RICARDO BOHORQUEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/23/2024 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 2/28/2024 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 2/28/2024 Not Ready for Inspection BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 3/4/2024 Approved SABAS ALONSO
Footing/Foundation/Slab 3/4/2024 Approved SABAS ALONSO
Footing/Foundation/Slab 3/5/2024 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/12/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 3/12/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/18/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/18/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 3/18/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/18/2024 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 3/18/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/20/2024 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 3/20/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/20/2024 Approved ALEJANDRO DE ARTOLA
Wood Frame 3/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/22/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 3/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 3/22/2024 Approved ALEJANDRO DE ARTOLA
Insulation 3/27/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 3/27/2024 Approved ALEJANDRO DE ARTOLA
Shower Pan 3/27/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 4/1/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 4/1/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 4/1/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 5/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/16/2024 Approved ALEJANDRO DE ARTOLA
Green Building Final 5/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 5/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 5/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 5/16/2024 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 5/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 5/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 5/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 5/20/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 6/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 6/24/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 6/24/2024 Approved ALEJANDRO DE ARTOLA
Service/Power Release 6/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 6/24/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/27/2024 Approved ALEJANDRO DE ARTOLA
Final 6/27/2024 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 6/27/2024 Approved ALEJANDRO DE ARTOLA
Final 9/30/2024 OK to Issue CofO ALEJANDRO DE ARTOLA