9565 N TEXHOMA AVE 91325

Certificate Information: 9565 N TEXHOMA AVE 91325

Application / Permit
23010-20000-04178
Plan Check / Job No.
B23VN14327
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD PER SB9 TWO UNIT DEVELOPMENT (1-STORY)
Permit Issued
Issued on 7/5/2024
Issuing Office
Current Status
Issued on 7/5/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/19/2023 APPLICANT
Assigned to Plan Check Engineer 10/25/2023 CARLOS MONTES
Corrections Issued 10/30/2023 CARLOS MONTES
Quality Review Completed 10/30/2023 PRANITA SHAH
Applicant returned to address corrections 5/30/2024 CARLOS MONTES
Applicant returned to address corrections 6/13/2024 CARLOS MONTES
Plan Check Approved 6/27/2024 CARLOS MONTES
Issued 7/5/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/22/2023 EDGAR ALCARAZ
Hydrant and Access approval Cleared 3/4/2024 MATTHEW CRAIG
Senate Bill 9 Cleared 3/11/2024 NELSON RODRIGUEZ
Construction near power lines Cleared 4/1/2024 RIDWAN HARDY
Grading Pre-Inspection Cleared 4/3/2024 CHARLES POWELL
Low Impact Development (LID) Cleared 5/20/2024 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 5/21/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 5/21/2024 EDGAR ALCARAZ
Sewer availability Cleared 5/21/2024 EDGAR ALCARAZ
GPI Written Notices Cleared 5/31/2024 CARLOS MONTES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/31/2024 Partial Approval MICHEL ABAJAN
Sewer 10/31/2024 Corrections Issued MICHEL ABAJAN
Sewer 11/8/2024 Approved JAVIER RAMOS JR
Underground Mechanical 11/8/2024 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 11/13/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 11/14/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 11/19/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 4/18/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/18/2025 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 4/18/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 4/24/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 5/13/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/15/2025 Corrections Issued NICHOLAS TROWBRIDGE
HVAC-Rough 7/15/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 7/15/2025 Approved NICHOLAS TROWBRIDGE
Wood Frame 7/15/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 9/4/2025 Corrections Issued NICHOLAS TROWBRIDGE
HVAC-Rough 9/4/2025 Approved NICHOLAS TROWBRIDGE
Insulation 9/4/2025 Corrections Issued NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 9/4/2025 Partial Approval NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 9/10/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 9/10/2025 Approved NICHOLAS TROWBRIDGE
Special/Order Compliance 9/10/2025 Corrections Issued NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 9/10/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 9/19/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Drywall Nailing 10/9/2025 Approved NICHOLAS TROWBRIDGE