16320 W RAYMER ST 91406

Certificate Information: 16320 W RAYMER ST 91406

Application / Permit
23010-20000-04143
Plan Check / Job No.
B23VN14194
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
NEW 183'11" X 200' ONE STORY WAREHOUSE AND OFFICE BLDG WITH MEZZANINE., NFPA-13 FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/23/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2023 APPLICANT
Assigned to Plan Check Engineer 10/26/2023 RARES BODEA
Assigned to Zoning Architect 10/26/2023 FRANCIS AHN
Disabled Access Plans Picked Up 10/31/2023 APPLICANT
Corrections Issued 11/2/2023 RARES BODEA
Green Plans Picked Up 11/6/2023 APPLICANT
Quality Review Completed 11/16/2023 STEVEN KIM
Building Plans Picked Up 11/16/2023 APPLICANT
Applicant returned to address corrections 12/26/2023 RARES BODEA
Applicant returned to address corrections 2/14/2024 RARES BODEA
Plan Check Approved 7/11/2024 RARES BODEA
Issued 8/23/2024 APPLICANT
CofO in Progress 12/19/2025 GREGORY POMISH
Permit Finaled 12/24/2025 JEFFREY DURAN
CofO Issued 12/24/2025 JEFFREY DURAN
Permit Finaled 12/24/2025 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 12/1/2023 CARLOS AGUILERA
Highway dedication Cleared 12/1/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/4/2023 CARLOS AGUILERA
Sewer availability Cleared 12/5/2023 CARLOS AGUILERA
Sewer availability Cleared 12/5/2023 CARLOS AGUILERA
Certificate of Compliance Cleared 12/15/2023 NELSON RODRIGUEZ
Tract Map conditions Cleared 12/15/2023 NELSON RODRIGUEZ
Tract Map conditions Cleared 12/15/2023 NELSON RODRIGUEZ
ZI Cleared 12/15/2023 NELSON RODRIGUEZ
Tract Map conditions Cleared 1/25/2024 NELSON RODRIGUEZ
Zoning Plan Check Cleared 4/3/2024 RARES BODEA
Prkng lot landscape/Water mgmt Cleared 5/2/2024 NATHAN ROMINE
Low Impact Development Cleared 5/7/2024 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 5/9/2024 CARLOS AGUILERA
Stormwater Pollution Mitigatn Cleared 5/10/2024 MARCO SANCHEZ
Green Code Cleared 5/14/2024 MICHAEL AYERS
DAS Clearance Cleared 5/23/2024 RARES BODEA
Hydrant and Access approval Cleared 7/3/2024 JOHN CONNEALLY

Contact Information

Architect Herdman,, Bridget Irene; Lic. No.: C32810 3800 E COAST HWY #6      CORONA DEL MAR, CA 92625
Contractor Millie And Severson Incorporated; Lic. No.: 99031-B P O BOX 3601      LOS ALAMITOS, CA 90720
Engineer Kramer,, David; Lic. No.: S2309 3002 DOW AVENUE SUITE 136      TUSTIN, CA 92680

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 9/4/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 9/4/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 9/5/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 9/16/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 9/23/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 9/24/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 9/25/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/26/2024 Conditional Approval GREGORY POMISH
Reinforced Concrete Frame 9/27/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 10/16/2024 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 10/16/2024 Partial Approval TIMOTHY POWELL
Deputy Reinf. Concrete 10/21/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 10/29/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/12/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 11/12/2024 Partial Approval GREGORY POMISH
Deputy Steel/Welding 11/14/2024 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 11/26/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 11/26/2024 Partial Approval GREGORY POMISH
Deputy Steel/Welding 12/5/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 12/6/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 12/9/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 12/10/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 12/10/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 12/10/2024 Partial Approval GREGORY POMISH
Deputy Steel/Welding 12/11/2024 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Partial Approval GREGORY POMISH
Green Building Rough 12/16/2024 Partial Inspection GREGORY POMISH
Structural Steel Frame 12/16/2024 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 12/16/2024 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 12/19/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 12/19/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 12/20/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 12/24/2024 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 12/30/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 12/31/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 1/6/2025 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 1/6/2025 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/9/2025 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Partial Approval GREGORY POMISH
Light Gage Steel Frame 1/30/2025 Partial Inspection GREGORY POMISH
Insulation 2/7/2025 Approved ROBERT DAVIS
T-Bar Ceiling 3/3/2025 Partial Inspection GREGORY POMISH
T-Bar Ceiling 3/20/2025 Not Ready for Inspection GREGORY POMISH
T-Bar Ceiling 3/24/2025 Partial Approval GREGORY POMISH
Drywall Nailing 11/12/2025 Approved GREGORY POMISH
Final 11/12/2025 Partial Inspection GREGORY POMISH
Footing/Foundation/Slab 11/12/2025 Approved GREGORY POMISH
Green Building Final 11/12/2025 Approved GREGORY POMISH
Green Building Rough 11/12/2025 Approved GREGORY POMISH
Reinforced Masonry Frame 11/12/2025 Approved GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 11/12/2025 SGSOV Approved GREGORY POMISH
Smoke Detectors 11/12/2025 Approved GREGORY POMISH
Structural Steel Frame 11/12/2025 Approved GREGORY POMISH
Verify Sprinkler Sign Off 11/12/2025 Approved GREGORY POMISH
Final 11/17/2025 Partial Inspection GREGORY POMISH
Final 11/21/2025 OK to Issue CofO GREGORY POMISH