- NEW 183'11" X 200' ONE STORY WAREHOUSE AND OFFICE BLDG WITH MEZZANINE., NFPA-13 FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 8/23/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2023 | RARES BODEA |
| Assigned to Zoning Architect | 10/26/2023 | FRANCIS AHN |
| Disabled Access Plans Picked Up | 10/31/2023 | APPLICANT |
| Corrections Issued | 11/2/2023 | RARES BODEA |
| Green Plans Picked Up | 11/6/2023 | APPLICANT |
| Quality Review Completed | 11/16/2023 | STEVEN KIM |
| Building Plans Picked Up | 11/16/2023 | APPLICANT |
| Applicant returned to address corrections | 12/26/2023 | RARES BODEA |
| Applicant returned to address corrections | 2/14/2024 | RARES BODEA |
| Plan Check Approved | 7/11/2024 | RARES BODEA |
| Issued | 8/23/2024 | APPLICANT |
| CofO in Progress | 12/19/2025 | GREGORY POMISH |
| Permit Finaled | 12/24/2025 | JEFFREY DURAN |
| CofO Issued | 12/24/2025 | JEFFREY DURAN |
| Permit Finaled | 12/24/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 12/1/2023 | CARLOS AGUILERA |
| Highway dedication | Cleared | 12/1/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/5/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/5/2023 | CARLOS AGUILERA |
| Certificate of Compliance | Cleared | 12/15/2023 | NELSON RODRIGUEZ |
| Tract Map conditions | Cleared | 12/15/2023 | NELSON RODRIGUEZ |
| Tract Map conditions | Cleared | 12/15/2023 | NELSON RODRIGUEZ |
| ZI | Cleared | 12/15/2023 | NELSON RODRIGUEZ |
| Tract Map conditions | Cleared | 1/25/2024 | NELSON RODRIGUEZ |
| Zoning Plan Check | Cleared | 4/3/2024 | RARES BODEA |
| Prkng lot landscape/Water mgmt | Cleared | 5/2/2024 | NATHAN ROMINE |
| Low Impact Development | Cleared | 5/7/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 5/9/2024 | CARLOS AGUILERA |
| Stormwater Pollution Mitigatn | Cleared | 5/10/2024 | MARCO SANCHEZ |
| Green Code | Cleared | 5/14/2024 | MICHAEL AYERS |
| DAS Clearance | Cleared | 5/23/2024 | RARES BODEA |
| Hydrant and Access approval | Cleared | 7/3/2024 | JOHN CONNEALLY |
Contact Information
| Architect | Herdman,, Bridget Irene; Lic. No.: C32810 | 3800 E COAST HWY #6 CORONA DEL MAR, CA 92625 |
| Contractor | Millie And Severson Incorporated; Lic. No.: 99031-B | P O BOX 3601 LOS ALAMITOS, CA 90720 |
| Engineer | Kramer,, David; Lic. No.: S2309 | 3002 DOW AVENUE SUITE 136 TUSTIN, CA 92680 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 9/4/2024 | Conditional Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 9/4/2024 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 9/5/2024 | Conditional Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 9/16/2024 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 9/23/2024 | Conditional Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 9/24/2024 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 9/25/2024 | Conditional Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 9/26/2024 | Conditional Approval | GREGORY POMISH |
| Reinforced Concrete Frame | 9/27/2024 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 10/16/2024 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 10/16/2024 | Partial Approval | TIMOTHY POWELL |
| Deputy Reinf. Concrete | 10/21/2024 | Conditional Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 10/29/2024 | Conditional Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 11/12/2024 | Conditional Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 11/12/2024 | Partial Approval | GREGORY POMISH |
| Deputy Steel/Welding | 11/14/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 11/26/2024 | Conditional Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 11/26/2024 | Partial Approval | GREGORY POMISH |
| Deputy Steel/Welding | 12/5/2024 | Conditional Approval | GREGORY POMISH |
| Deputy Steel/Welding | 12/6/2024 | Conditional Approval | GREGORY POMISH |
| Deputy Steel/Welding | 12/9/2024 | Conditional Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 12/10/2024 | Conditional Approval | GREGORY POMISH |
| Deputy Steel/Welding | 12/10/2024 | Conditional Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 12/10/2024 | Partial Approval | GREGORY POMISH |
| Deputy Steel/Welding | 12/11/2024 | Conditional Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2024 | Partial Approval | GREGORY POMISH |
| Green Building Rough | 12/16/2024 | Partial Inspection | GREGORY POMISH |
| Structural Steel Frame | 12/16/2024 | Partial Approval | GREGORY POMISH |
| Verify Sprinkler Sign Off | 12/16/2024 | Partial Inspection | GREGORY POMISH |
| Deputy Reinf. Concrete | 12/19/2024 | Conditional Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 12/19/2024 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 12/20/2024 | Conditional Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 12/24/2024 | Partial Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 12/30/2024 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 12/31/2024 | Conditional Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 1/6/2025 | Conditional Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 1/6/2025 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 1/9/2025 | Conditional Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | Partial Approval | GREGORY POMISH |
| Light Gage Steel Frame | 1/30/2025 | Partial Inspection | GREGORY POMISH |
| Insulation | 2/7/2025 | Approved | ROBERT DAVIS |
| T-Bar Ceiling | 3/3/2025 | Partial Inspection | GREGORY POMISH |
| T-Bar Ceiling | 3/20/2025 | Not Ready for Inspection | GREGORY POMISH |
| T-Bar Ceiling | 3/24/2025 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 11/12/2025 | Approved | GREGORY POMISH |
| Final | 11/12/2025 | Partial Inspection | GREGORY POMISH |
| Footing/Foundation/Slab | 11/12/2025 | Approved | GREGORY POMISH |
| Green Building Final | 11/12/2025 | Approved | GREGORY POMISH |
| Green Building Rough | 11/12/2025 | Approved | GREGORY POMISH |
| Reinforced Masonry Frame | 11/12/2025 | Approved | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 11/12/2025 | SGSOV Approved | GREGORY POMISH |
| Smoke Detectors | 11/12/2025 | Approved | GREGORY POMISH |
| Structural Steel Frame | 11/12/2025 | Approved | GREGORY POMISH |
| Verify Sprinkler Sign Off | 11/12/2025 | Approved | GREGORY POMISH |
| Final | 11/17/2025 | Partial Inspection | GREGORY POMISH |
| Final | 11/21/2025 | OK to Issue CofO | GREGORY POMISH |