16161 W RAYMER ST 91406

Certificate Information: 16161 W RAYMER ST 91406

Application / Permit
23010-20000-04138
Plan Check / Job No.
B23VN14187
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
NEW 199' X 285' 1-STORY TYPE III-B WAREHOUSE W/ OFFICE BUILDING.
Permit Issued
Issued on 8/19/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2023 APPLICANT
Assigned to Plan Check Engineer 10/26/2023 RAPHAEL ROSAS
Assigned to Zoning Architect 10/26/2023 FRANCIS AHN
Corrections Issued 11/6/2023 RAPHAEL ROSAS
Disabled Access Plans Picked Up 11/6/2023 APPLICANT
Green Plans Picked Up 11/6/2023 APPLICANT
Quality Review Completed 11/7/2023 STEVEN KIM
Building Plans Picked Up 11/8/2023 APPLICANT
Applicant returned to address corrections 2/29/2024 RAPHAEL ROSAS
Applicant returned to address corrections 6/6/2024 RAPHAEL ROSAS
Plan Check Approved 7/8/2024 RAPHAEL ROSAS
No Progress 7/10/2024 RAPHAEL ROSAS
Plan Check Approved 7/10/2024 RAPHAEL ROSAS
Issued 8/19/2024 APPLICANT
CofO in Progress 1/2/2026 GREGORY POMISH
Permit Finaled 1/20/2026 RICKEY JACKSON
Permit Finaled 1/20/2026 RICKEY JACKSON
CofO Issued 1/20/2026 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 11/16/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 11/16/2023 COLIN LOREDO
Sewer availability Cleared 12/2/2023 COLIN LOREDO
Highway dedication Cleared 1/30/2024 COLIN LOREDO
Driveway location Cleared 3/5/2024 MIGUEL CRISOSTOMO
Internal circulation Cleared 3/5/2024 MIGUEL CRISOSTOMO
Trees in Parkway Cleared 4/5/2024 ADALBERTO VERA
Low Impact Development (LID) Cleared 4/10/2024 MARCO SANCHEZ
Permit Cleared 4/10/2024 CARLOS AGUILERA
Prkng lot landscape/Water mgmt Cleared 4/22/2024 ROSALINDA MEZA
Zoning Plan Check Cleared 4/22/2024 RAPHAEL ROSAS
Roof/Waste drainage to street Cleared 5/14/2024 CARLOS AGUILERA
Green Code Cleared 5/21/2024 MICHAEL AYERS
DAS Clearance Cleared 5/23/2024 RAPHAEL ROSAS
Hydrant and Access approval Cleared 6/4/2024 RUEL COLE
Metro Rail approval Cleared 6/28/2024 JENNIFER SU

Contact Information

Architect Herdman,, Bridget Irene; Lic. No.: C32810 100 BAYVIEW CIR #100      NEWPORT BEACH, CA 92660
Contractor Millie And Severson Incorporated; Lic. No.: 99031-B P O BOX 3601      LOS ALAMITOS, CA 90720
Engineer Delgadillo,, Christian; Lic. No.: GE3144 10828 CORD AVE      DOWNEY, CA 90241
Engineer Kramer,, David; Lic. No.: S2309 3002 DOW AVENUE SUITE 136      TUSTIN, CA 92680
Geologist Hull,, Jeff Lee; Lic. No.: EG2056 266 AVENIDA VICTORIA APT C      SAN CLEMENTE, CA 92672

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 8/26/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 8/26/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 8/27/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 8/27/2024 Corrections Issued GREGORY POMISH
Deputy Reinf. Concrete 8/28/2024 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 8/28/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 8/29/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/5/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/9/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 9/9/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 9/10/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/17/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/18/2024 Conditional Approval GREGORY POMISH
Green Building Rough 9/20/2024 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 9/20/2024 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 9/20/2024 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 9/24/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 9/24/2024 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 10/10/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/11/2024 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 10/21/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 10/22/2024 Conditional Approval GREGORY POMISH
Green Building Rough 10/22/2024 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 10/22/2024 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 10/22/2024 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 10/23/2024 Conditional Approval GREGORY POMISH
Green Building Rough 10/28/2024 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 10/28/2024 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 10/28/2024 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 10/31/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 10/31/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 10/31/2024 Partial Approval GREGORY POMISH
Deputy Steel/Welding 11/4/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/7/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 11/7/2024 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 11/12/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 11/13/2024 Conditional Approval GREGORY POMISH
Green Building Rough 11/13/2024 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 11/13/2024 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 11/13/2024 Not Ready for Inspection GREGORY POMISH
Deputy Steel/Welding 11/14/2024 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Partial Inspection GREGORY POMISH
Structural Steel Frame 11/19/2024 Partial Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Partial Inspection GREGORY POMISH
Structural Steel Frame 11/22/2024 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 11/26/2024 Conditional Approval GREGORY POMISH
Deputy Wood Construction 11/26/2024 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 11/26/2024 Partial Approval GREGORY POMISH
Structural Steel Frame 11/26/2024 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 12/3/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 12/3/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 12/4/2024 Conditional Approval GREGORY POMISH
Deputy Drilled-In Anchors 12/5/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 12/5/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 12/10/2024 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 12/24/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 12/24/2024 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 12/27/2024 Conditional Approval GREGORY POMISH
Deputy Wood Construction 1/8/2025 Conditional Approval GREGORY POMISH
Light Gage Steel Frame 1/16/2025 Partial Approval GREGORY POMISH
Wood Frame 1/16/2025 Partial Approval GREGORY POMISH
Insulation 1/24/2025 Partial Approval GREGORY POMISH
Light Gage Steel Frame 1/24/2025 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Partial Approval GREGORY POMISH
T-Bar Ceiling 3/3/2025 Partial Inspection GREGORY POMISH
Deputy Drilled-In Anchors 8/22/2025 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/25/2025 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/26/2025 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/4/2025 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/5/2025 Approved JOHN KITCKO
T-Bar Ceiling 11/13/2025 Partial Approval GREGORY POMISH
Drywall Nailing 12/17/2025 Approved GREGORY POMISH
Final 12/17/2025 OK to Issue CofO GREGORY POMISH
Footing/Foundation/Slab 12/17/2025 Approved GREGORY POMISH
Green Building Final 12/17/2025 Approved GREGORY POMISH
Green Building Rough 12/17/2025 Approved GREGORY POMISH
Reinforced Concrete Frame 12/17/2025 Approved GREGORY POMISH
Reinforced Masonry Frame 12/17/2025 Approved GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 12/17/2025 SGSOV No Gas GREGORY POMISH
Smoke Detectors 12/17/2025 Approved GREGORY POMISH
Verify Sprinkler Sign Off 12/17/2025 Approved GREGORY POMISH
Final 12/26/2025 Partial Inspection DEANDRE HOFFMAN