14306 W OSBORNE ST 91402

Certificate Information: 14306 W OSBORNE ST 91402

Application / Permit
23010-20000-04058
Plan Check / Job No.
B23VN13855
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1 STORY ACCESSORY DWELLING UNIT; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 4/23/2024
Issuing Office
Valley
Current Status
CofO Issued on 6/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2023 APPLICANT
Assigned to Plan Check Engineer 10/19/2023 SELLA BENYAMIN
Corrections Issued 10/26/2023 SELLA BENYAMIN
Quality Review Completed 10/30/2023 STEVEN KIM
Building Plans Picked Up 10/31/2023 APPLICANT
Applicant returned to address corrections 11/16/2023 SELLA BENYAMIN
Applicant returned to address corrections 11/22/2023 SELLA BENYAMIN
Applicant returned to address corrections 2/29/2024 SELLA BENYAMIN
Plan Check Approved 4/23/2024 SELLA BENYAMIN
Issued 4/23/2024 APPLICANT
CofO in Progress 5/15/2025 VINCENT HANLEY
Permit Finaled 6/12/2025 RUBEN SALAS
CofO Issued 6/12/2025 RUBEN SALAS
Permit Finaled 6/12/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 1/29/2024 SAMUEL LINN
Address approval Cleared 1/31/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 1/31/2024 BRYAN GODINEZ
Hydrant and Access approval Cleared 1/31/2024 LAVEON RIDER
Roof/Waste drainage to street Cleared 1/31/2024 BRYAN GODINEZ
Sewer availability Cleared 1/31/2024 BRYAN GODINEZ
Construction near power lines Cleared 4/11/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/29/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 8/29/2024 Approved VINCENT HANLEY
PLUMBING-Rough 9/16/2024 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 9/25/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Partial Approval VINCENT HANLEY
Insulation 9/25/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Approved VINCENT HANLEY
PLUMBING-Rough 10/25/2024 Approved VINCENT HANLEY
ELECTRICAL-Rough 10/30/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 11/5/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Approved VINCENT HANLEY
Green Building Rough 11/5/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/5/2024 Partial Approval VINCENT HANLEY
Verify Sprinkler Sign Off 11/5/2024 Approved VINCENT HANLEY
Insulation 11/18/2024 Approved VINCENT HANLEY
Drywall Nailing 11/20/2024 Approved GREGG CUMMINGS
ELECTRICAL-Final 5/15/2025 Approved VINCENT HANLEY
Final 5/15/2025 OK to Issue CofO VINCENT HANLEY
Green Building Final 5/15/2025 Approved VINCENT HANLEY
HVAC-Final 5/15/2025 Approved VINCENT HANLEY
PLUMBING-Final 5/15/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/15/2025 SGSOV Not Required VINCENT HANLEY
Service/Power Release 5/15/2025 Approved VINCENT HANLEY
Smoke Detectors 5/15/2025 Approved VINCENT HANLEY