9309 N ENCINO AVE 91325
Certificate Information: 9309 N ENCINO AVE 91325
- Application / Permit
- 23010-20000-04054
- Plan Check / Job No.
- B23VN13835
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: New Detached 1-Story ADU per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 5/8/2024
- Issuing Office
- Current Status
- CofO Issued on 2/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2023 | DAVID CASTILLO |
| Corrections Issued | 10/14/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 10/26/2023 | DAVID CASTILLO |
| Plan Check Approved | 2/6/2024 | DAVID CASTILLO |
| Issued | 5/8/2024 | APPLICANT |
| CofO in Progress | 1/21/2026 | CHRISTOPHER ROJAS |
| Permit Finaled | 2/3/2026 | RUBEN SALAS |
| CofO Issued | 2/3/2026 | RUBEN SALAS |
| Permit Finaled | 2/3/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2023 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2023 | BRYAN GODINEZ |
| Sewer availability | Cleared | 10/23/2023 | BRYAN GODINEZ |
| Low Impact Development (LID) | Cleared | 12/5/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 12/5/2023 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/5/2023 | LEE GUILBEAUX |
| Construction within easement | Cleared | 2/3/2024 | RIDWAN HARDY |
Contact Information
| Contractor | L A Construction Group Inc; Lic. No.: 873259-B | , |
| Contractor | L A Hardwood Floors & Remodeling Inc; Lic. No.: 873259-B | , |
| Engineer | Nalbandian,, Serop Krekor; Lic. No.: M39801 | 1236 N COLUMBUS AVE UNIT 4 GLENDALE, CA 91202 |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/15/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/3/2024 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 6/3/2024 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 6/7/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/10/2024 | Partial Inspection | JAVIER RAMOS JR |
| Sewer | 6/10/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 6/10/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/16/2024 | Partial Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 7/16/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 7/16/2024 | Partial Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/16/2024 | Approved | JAVIER RAMOS JR |
| Deputy Wood Construction | 7/23/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 8/1/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/3/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/3/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 9/3/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 9/3/2024 | Partial Inspection | JAVIER RAMOS JR |
| Insulation | 9/30/2024 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/30/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/9/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 10/9/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 10/9/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 10/9/2024 | Approved | JAVIER RAMOS JR |
| Shower Pan | 10/9/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/16/2024 | Approved | LOUIS ESCOTO |
| Pre-Inspection | 1/17/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 1/17/2025 | Approved | JAVIER RAMOS JR |
| Final | 5/12/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 5/12/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/12/2025 | SGSOV Not Required | CHRISTOPHER ROJAS |
| Service/Power Release | 5/12/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 5/12/2025 | Approved | CHRISTOPHER ROJAS |
| Pre-Inspection | 5/29/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Final | 7/1/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Final | 11/7/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 11/7/2025 | Approved | NICHOLAS TROWBRIDGE |
| Service/Power Release | 11/7/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 1/8/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Service/Power Release | 1/8/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 1/21/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 1/21/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 1/21/2026 | Approved | CHRISTOPHER ROJAS |