10017 N MASON AVE 91311
Certificate Information: 10017 N MASON AVE 91311
- Application / Permit
- 23010-20000-04048
- Plan Check / Job No.
- B23VN13827
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Construct detached irregular shaped 41' 9" x 22' 1"single family dwelling unit per SB 9. NFPA 13D sprinkler is required thru-out. All work done per engineer.
- Permit Issued
- Issued on 4/11/2024
- Issuing Office
- Current Status
- CofO Corrected on 10/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2023 | NAREG ATARIAN |
| Corrections Issued | 10/20/2023 | NAREG ATARIAN |
| Quality Review Completed | 11/1/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 11/6/2023 | NAREG ATARIAN |
| Applicant returned to address corrections | 2/15/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 2/22/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 4/5/2024 | NAREG ATARIAN |
| Plan Check Approved | 4/8/2024 | NAREG ATARIAN |
| Issued | 4/11/2024 | APPLICANT |
| CofO in Progress | 8/29/2025 | DAVID SCANTLIN |
| CofO Issued-Status Void | 9/6/2025 | MICHAEL PELHAM |
| Permit Finaled-Status Void | 9/6/2025 | MICHAEL PELHAM |
| Re-Activate Permit | 9/16/2025 | MICHAEL PELHAM |
| Permit Finaled | 10/4/2025 | MICHAEL PELHAM |
| Permit Finaled | 10/4/2025 | MICHAEL PELHAM |
| CofO Corrected | 10/4/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 11/21/2023 | EDGAR ALCARAZ |
| Highway dedication | Cleared | 11/21/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2023 | BRYAN GODINEZ |
| Sewer availability | Cleared | 11/22/2023 | BRYAN GODINEZ |
| Senate Bill 9 | Cleared | 11/27/2023 | NELSON RODRIGUEZ |
| Miscellaneous | Cleared | 11/28/2023 | MIGUEL CRISOSTOMO |
| Hydrant and Access approval | Cleared | 12/1/2023 | LAVEON RIDER |
| Miscellaneous | Cleared | 12/7/2023 | RONY GIRON |
| Low Impact Development (LID) | Cleared | 2/8/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 2/8/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grandhi,, Venkata Rohit; Lic. No.: C88709 | 7823 BOXWOOD CT HIGHLAND, CA 92346 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/18/2024 | Partial Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 6/24/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 11/21/2024 | Corrections Issued | DAVID SCANTLIN |
| Green Building Rough | 11/21/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 11/21/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 12/16/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 12/16/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 1/23/2025 | Approved | KRISTEN CAUSEY |
| PLUMBING-Rough | 1/23/2025 | No Access for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 1/24/2025 | Corrections Issued | KRISTEN CAUSEY |
| PLUMBING-Rough | 3/4/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/5/2025 | Corrections Issued | DAVID SCANTLIN |
| Green Building Rough | 3/5/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Special/Order Compliance | 3/5/2025 | Partial Inspection | HENRY KIM |
| Verify Sprinkler Sign Off | 3/5/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Special/Order Compliance | 3/6/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 3/20/2025 | Conditional Approval | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 3/21/2025 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/28/2025 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Approved | DAVID SCANTLIN |
| Green Building Rough | 3/28/2025 | Approved | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 3/28/2025 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 3/28/2025 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 4/7/2025 | Approved | DAVID SCANTLIN |
| Insulation | 4/7/2025 | Partial Approval | DAVID SCANTLIN |
| Shower Pan | 4/7/2025 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 4/11/2025 | Approved | DAVID SCANTLIN |
| Final | 7/2/2025 | Corrections Issued | DAVID SCANTLIN |
| Footing/Foundation/Slab | 7/2/2025 | Approved | DAVID SCANTLIN |
| Green Building Final | 7/2/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 7/2/2025 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 7/2/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 7/2/2025 | Approved | DAVID SCANTLIN |
| Final | 7/30/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 7/30/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Service/Power Release | 7/30/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 8/29/2025 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 8/29/2025 | Approved | DAVID SCANTLIN |
| Service/Power Release | 8/29/2025 | Approved | DAVID SCANTLIN |