6908 N COLBATH AVE 91405

Certificate Information: 6908 N COLBATH AVE 91405

Application / Permit
23010-20000-04044
Plan Check / Job No.
B23VN13811
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 22'6" X 40'1" DETACHED, FULLY ELECTRIC ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d). WORK TO BE DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 5/3/2024
Issuing Office
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2023 APPLICANT
Assigned to Plan Check Engineer 10/13/2023 MADISON ODELL
Corrections Issued 10/14/2023 MADISON ODELL
Applicant returned to address corrections 12/6/2023 MADISON ODELL
Applicant returned to address corrections 2/26/2024 MADISON ODELL
Applicant returned to address corrections 4/10/2024 MADISON ODELL
Applicant returned to address corrections 4/27/2024 MADISON ODELL
Plan Check Approved 5/1/2024 MADISON O'DELL
Issued 5/3/2024 APPLICANT
CofO in Progress 4/1/2025 RYAN SALAZAR
Permit Finaled 5/15/2025 RUBEN SALAS
Permit Finaled 5/15/2025 RUBEN SALAS
CofO Issued 5/15/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/3/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 11/7/2023 EDGAR ALCARAZ
Sewer availability Cleared 11/7/2023 EDGAR ALCARAZ
Construction near power lines Cleared 4/25/2024 TINA MIRANDA
Low Impact Development (LID) Cleared 4/25/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/29/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/29/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/28/2024 Partial Approval RYAN SALAZAR
Underground Mechanical 6/28/2024 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 7/8/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/2/2024 Approved RYAN SALAZAR
PLUMBING-Rough 8/27/2024 Approved RYAN SALAZAR
Underground Mechanical 8/29/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 9/9/2024 Partial Approval RYAN SALAZAR
HVAC-Rough 9/9/2024 Approved RYAN SALAZAR
PLUMBING-Rough 9/9/2024 Approved RYAN SALAZAR
Insulation 9/23/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/23/2024 Partial Approval RYAN SALAZAR
Drywall Nailing 10/7/2024 Approved RYAN SALAZAR
Shower Pan 10/7/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 12/16/2024 Approved RYAN SALAZAR
Final 12/16/2024 Corrections Issued RYAN SALAZAR
Green Building Final 12/16/2024 Approved RYAN SALAZAR
Green Building Rough 12/16/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Not Required RYAN SALAZAR
Service/Power Release 12/16/2024 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 12/16/2024 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 12/16/2024 Approved RYAN SALAZAR
Final 2/26/2025 No Access for Inspection RYAN SALAZAR
Service/Power Release 2/26/2025 No Access for Inspection RYAN SALAZAR
Final 2/28/2025 Corrections Issued RYAN SALAZAR
Final 3/27/2025 OK to Issue CofO RYAN SALAZAR
Service/Power Release 3/27/2025 Approved RYAN SALAZAR