1004 3/4 E 76TH ST 90001

Certificate Information: 1004 3/4 E 76TH ST 90001

Application / Permit
23010-20000-04039
Plan Check / Job No.
B23VN13795
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New detached ADU per LAMC 12.22 A.33 (c)-(d). All Work Done per WFPP.
Permit Issued
Issued on 1/26/2024
Issuing Office
Current Status
CofO Issued on 10/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2023 APPLICANT
Assigned to Plan Check Engineer 10/16/2023 GIOVANNY CHAVEZ
Corrections Issued 10/17/2023 GIOVANNY CHAVEZ
Applicant returned to address corrections 11/23/2023 SARKIS HARABEDIAN
Applicant returned to address corrections 12/2/2023 CAROLEAN BASMA
Applicant returned to address corrections 12/7/2023 DAVID CASTILLO
Plan Check Approved 1/24/2024 DAVID CASTILLO
Issued 1/26/2024 SUYA LY
CofO in Progress 10/4/2024 ALEJANDRO DE ARTOLA
Permit Finaled 10/15/2024 RUBEN SALAS
CofO Issued 10/15/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/17/2023 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 11/17/2023 CHRISTINA BRACO
Sewer availability Cleared 11/17/2023 CHRISTINA BRACO
Low Impact Development (LID) Cleared 11/20/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 11/21/2023 JUSTIN BICOL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/29/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 3/29/2024 Not Ready for Inspection MICHAEL LEWIS
Underground Mechanical 3/29/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 4/3/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Conditional Approval MICHAEL LEWIS
BUILDING-Rough-Frame 5/28/2024 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 5/28/2024 Corrections Issued CRAIG DAVIS
Green Building Rough 5/28/2024 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 5/28/2024 Approved CRAIG DAVIS
PLUMBING-Rough 5/28/2024 Corrections Issued CRAIG DAVIS
Verify Sprinkler Sign Off 5/28/2024 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 6/6/2024 Approved MICHAEL LEWIS
ELECTRICAL-Rough 6/6/2024 Approved MICHAEL LEWIS
Green Building Rough 6/6/2024 Approved MICHAEL LEWIS
HVAC-Rough 6/6/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 6/6/2024 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 6/6/2024 Approved MICHAEL LEWIS
Insulation 6/12/2024 Approved MICHAEL LEWIS
Drywall Nailing 6/17/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 6/17/2024 Approved JOSH MEISTER
Sewer 7/10/2024 Approved MICHAEL LEWIS
Underground Mechanical 7/10/2024 Approved MICHAEL LEWIS
Underground Mechanical 8/6/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 10/3/2024 Approved ALEJANDRO DE ARTOLA
Final 10/3/2024 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 10/3/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 10/3/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 10/3/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/3/2024 SGSOV Not Required ALEJANDRO DE ARTOLA
Service/Power Release 10/3/2024 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 10/3/2024 Approved ALEJANDRO DE ARTOLA