1004 3/4 E 76TH ST 90001
Certificate Information: 1004 3/4 E 76TH ST 90001
- Application / Permit
- 23010-20000-04039
- Plan Check / Job No.
- B23VN13795
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New detached ADU per LAMC 12.22 A.33 (c)-(d). All Work Done per WFPP.
- Permit Issued
- Issued on 1/26/2024
- Issuing Office
- Current Status
- CofO Issued on 10/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2023 | GIOVANNY CHAVEZ |
| Corrections Issued | 10/17/2023 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 11/23/2023 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 12/2/2023 | CAROLEAN BASMA |
| Applicant returned to address corrections | 12/7/2023 | DAVID CASTILLO |
| Plan Check Approved | 1/24/2024 | DAVID CASTILLO |
| Issued | 1/26/2024 | SUYA LY |
| CofO in Progress | 10/4/2024 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 10/15/2024 | RUBEN SALAS |
| CofO Issued | 10/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 11/17/2023 | CHRISTINA BRACO |
| Low Impact Development (LID) | Cleared | 11/20/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 11/21/2023 | JUSTIN BICOL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/29/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 3/29/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Underground Mechanical | 3/29/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 4/3/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2024 | Conditional Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 5/28/2024 | Not Ready for Inspection | CRAIG DAVIS |
| ELECTRICAL-Rough | 5/28/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 5/28/2024 | Not Ready for Inspection | CRAIG DAVIS |
| HVAC-Rough | 5/28/2024 | Approved | CRAIG DAVIS |
| PLUMBING-Rough | 5/28/2024 | Corrections Issued | CRAIG DAVIS |
| Verify Sprinkler Sign Off | 5/28/2024 | Not Ready for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 6/6/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/6/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 6/6/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 6/6/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 6/6/2024 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 6/6/2024 | Approved | MICHAEL LEWIS |
| Insulation | 6/12/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 6/17/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 6/17/2024 | Approved | JOSH MEISTER |
| Sewer | 7/10/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 7/10/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 8/6/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 10/3/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/3/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/3/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/3/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/3/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/3/2024 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/3/2024 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 10/3/2024 | Approved | ALEJANDRO DE ARTOLA |