14758 W MORRISON ST 91403

Certificate Information: 14758 W MORRISON ST 91403

Application / Permit
23010-20000-04028
Plan Check / Job No.
B23VN13742
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 36' X 64'-6" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 1/5/2024
Issuing Office
Valley
Current Status
CofO Issued on 2/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 SELLA BENYAMIN
Corrections Issued 10/17/2023 SELLA BENYAMIN
Quality Review Completed 10/18/2023 STEVEN KIM
Building Plans Picked Up 10/19/2023 APPLICANT
Plan Check Approved 12/28/2023 SELLA BENYAMIN
Issued 1/5/2024 APPLICANT
CofO in Progress 1/27/2025 JACK KARGODORIAN
Permit Finaled 2/20/2025 RUBEN SALAS
CofO Issued 2/20/2025 RUBEN SALAS
Permit Finaled 2/20/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/24/2023 TAL SHEMEN
Sewer availability Cleared 10/24/2023 TAL SHEMEN
ZI Cleared 10/24/2023 STEVEN WECHSLER
Hydrant and Access approval Cleared 10/28/2023 LAVEON RIDER
Low Impact Development (LID) Cleared 12/5/2023 TRISH PARAS
Roof/Waste drainage to street Cleared 12/6/2023 NIKKI ZULUETA
Permit Cleared 12/20/2023 JOHN LIN
Trees in Parkway Cleared 12/20/2023 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 2/29/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 3/4/2024 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 3/4/2024 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 3/4/2024 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 3/6/2024 Corrections Issued THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 3/7/2024 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 3/13/2024 Conditional Approval THOMAS FINNILA
Underground Mechanical 3/13/2024 Partial Inspection THOMAS FINNILA
Footing/Foundation/Slab 3/22/2024 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/5/2024 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Partial Approval THOMAS FINNILA
Deputy Wood Construction 4/15/2024 Conditional Approval DAVID MATSON
PLUMBING-Rough 5/6/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 5/8/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 5/10/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 5/10/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 5/10/2024 Approved THOMAS FINNILA
ELECTRICAL-Rough 5/16/2024 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 5/16/2024 Approved JACK KARGODORIAN
ELECTRICAL-Rough 5/29/2024 Approved JACK KARGODORIAN
Shower Pan 5/29/2024 Approved JACK KARGODORIAN
Wood Frame 5/29/2024 Corrections Issued JACK KARGODORIAN
Deputy Steel/Welding 5/31/2024 Conditional Approval ROBERT GOLD
Deputy Wood Construction 5/31/2024 Conditional Approval ROBERT GOLD
Wood Frame 5/31/2024 Corrections Issued JACK KARGODORIAN
Interior/Exterior Lathing 6/4/2024 Partial Approval JACK KARGODORIAN
Wood Frame 6/4/2024 Approved JACK KARGODORIAN
Insulation 6/7/2024 Approved JACK KARGODORIAN
Insulation 6/10/2024 Approved JACK KARGODORIAN
Drywall Nailing 6/12/2024 Corrections Issued SALVADOR MARTINEZ
Drywall Nailing 6/13/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 6/13/2024 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 6/17/2024 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 12/12/2024 Partial Approval JACK KARGODORIAN
Final 12/12/2024 Corrections Issued JACK KARGODORIAN
Green Building Final 12/12/2024 Approved JACK KARGODORIAN
Green Building Rough 12/12/2024 Approved JACK KARGODORIAN
MERV13>=Final 12/12/2024 Approved JACK KARGODORIAN
MERV13>=Rough 12/12/2024 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/12/2024 SGSOV Not Required JACK KARGODORIAN
Service/Power Release 12/12/2024 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 12/12/2024 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 12/12/2024 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 1/24/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 1/24/2025 Approved JACK KARGODORIAN
Final 1/24/2025 OK to Issue CofO JACK KARGODORIAN
HVAC-Final 1/24/2025 Approved JACK KARGODORIAN
PLUMBING-Final 1/24/2025 Approved JACK KARGODORIAN
Service/Power Release 1/24/2025 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 1/24/2025 Approved JACK KARGODORIAN