6653 N CANTALOUPE AVE 91405
Certificate Information: 6653 N CANTALOUPE AVE 91405
- Application / Permit
- 23010-20000-04025
- Plan Check / Job No.
- B23VN13730
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 21' X 32' (2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 1/26/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2023 | SELLA BENYAMIN |
| Corrections Issued | 10/17/2023 | SELLA BENYAMIN |
| Quality Review Completed | 10/18/2023 | STEVEN KIM |
| Building Plans Picked Up | 10/25/2023 | APPLICANT |
| Plan Check Approved | 1/25/2024 | SELLA BENYAMIN |
| Issued | 1/26/2024 | APPLICANT |
| CofO in Progress | 6/12/2024 | RYAN SALAZAR |
| Permit Finaled | 6/21/2024 | RUBEN SALAS |
| CofO Issued | 6/21/2024 | RUBEN SALAS |
| Permit Finaled | 6/21/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 10/23/2023 | COLIN LOREDO |
| Low Impact Development (LID) | Cleared | 11/21/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 11/21/2023 | BRYAN GODINEZ |
| Construction near power lines | Cleared | 1/8/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/8/2024 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 2/13/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2024 | Partial Approval | RYAN SALAZAR |
| Special/Order Compliance | 2/21/2024 | Corrections Issued | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 2/21/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2024 | Corrections Issued | RYAN SALAZAR |
| ELECTRICAL-Rough | 3/13/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 3/13/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 3/13/2024 | Approved | RYAN SALAZAR |
| Insulation | 3/18/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/18/2024 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/26/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 3/26/2024 | Corrections Issued | THOMAS FINNILA |
| Drywall Nailing | 3/29/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/29/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 3/29/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 5/10/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 5/17/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/23/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 5/23/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV Not Ready | RYAN SALAZAR |
| Service/Power Release | 5/23/2024 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/29/2024 | Approved | RYAN SALAZAR |
| Final | 5/29/2024 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 5/29/2024 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/29/2024 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 5/29/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 5/29/2024 | Approved | RYAN SALAZAR |
| Final | 6/11/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 6/11/2024 | Approved | RYAN SALAZAR |
| Service/Power Release | 6/11/2024 | Approved | RYAN SALAZAR |