15434 W SEPTO ST 91345
Certificate Information: 15434 W SEPTO ST 91345
- Application / Permit
- 23010-20000-03990
- Plan Check / Job No.
- B23VN13545
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW FULLY ELECTRIC, DETACHED, IRREGULARLY SHAPED ACCESSORY DWELLING UNIT (1200 SF) PER LAMC 12.22.A.33(c) AND (d). WORK TO BE DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 5/15/2024
- Issuing Office
- Current Status
- CofO Issued on 6/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2023 | MADISON ODELL |
| Corrections Issued | 12/1/2023 | MADISON ODELL |
| Plan Check Approved | 5/15/2024 | MADISON O'DELL |
| Issued | 5/15/2024 | APPLICANT |
| CofO in Progress | 6/12/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 6/20/2025 | RUBEN SALAS |
| CofO Issued | 6/20/2025 | RUBEN SALAS |
| Permit Finaled | 6/20/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/19/2023 | GABRIELLA TORRES |
| Construction near power lines | Cleared | 4/5/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 4/5/2024 | WALTER RAMIREZ |
| Miscellaneous | Cleared | 4/8/2024 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 4/8/2024 | STEVEN WECHSLER |
| Low Impact Development (LID) | Cleared | 4/10/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 4/23/2024 | GABRIELLA TORRES |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2024 | GABRIELLA TORRES |
| Miscellaneous | Cleared | 4/25/2024 | GABRIELLA TORRES |
| Sewer availability | Cleared | 4/25/2024 | GABRIELLA TORRES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: NA76761 | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/17/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 5/23/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 6/7/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/26/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 6/26/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/26/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 6/26/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 6/26/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 6/26/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 8/12/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/12/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 8/12/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/23/2024 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/25/2024 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 9/25/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/25/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 9/27/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 9/30/2024 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/10/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 10/10/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/10/2024 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 10/10/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 1/28/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 1/28/2025 | Approved | JENNIFER RABUCHIN |
| Final | 4/29/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 4/29/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/14/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 5/14/2025 | Partial Inspection | JENNIFER RABUCHIN |
| HVAC-Final | 5/14/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/14/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 5/14/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 6/11/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 6/11/2025 | Approved | JENNIFER RABUCHIN |