15434 W SEPTO ST 91345

Certificate Information: 15434 W SEPTO ST 91345

Application / Permit
23010-20000-03990
Plan Check / Job No.
B23VN13545
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW FULLY ELECTRIC, DETACHED, IRREGULARLY SHAPED ACCESSORY DWELLING UNIT (1200 SF) PER LAMC 12.22.A.33(c) AND (d). WORK TO BE DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 5/15/2024
Issuing Office
Current Status
CofO Issued on 6/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2023 APPLICANT
Assigned to Plan Check Engineer 11/30/2023 MADISON ODELL
Corrections Issued 12/1/2023 MADISON ODELL
Plan Check Approved 5/15/2024 MADISON O'DELL
Issued 5/15/2024 APPLICANT
CofO in Progress 6/12/2025 JENNIFER RABUCHIN
Permit Finaled 6/20/2025 RUBEN SALAS
CofO Issued 6/20/2025 RUBEN SALAS
Permit Finaled 6/20/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/19/2023 GABRIELLA TORRES
Construction near power lines Cleared 4/5/2024 WALTER RAMIREZ
Construction within easement Cleared 4/5/2024 WALTER RAMIREZ
Miscellaneous Cleared 4/8/2024 STEVEN WECHSLER
Miscellaneous Cleared 4/8/2024 STEVEN WECHSLER
Low Impact Development (LID) Cleared 4/10/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 4/23/2024 GABRIELLA TORRES
Eng Process Fee Ord 176,300 Cleared 4/25/2024 GABRIELLA TORRES
Miscellaneous Cleared 4/25/2024 GABRIELLA TORRES
Sewer availability Cleared 4/25/2024 GABRIELLA TORRES

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: NA76761       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/17/2024 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 5/23/2024 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 6/7/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 6/26/2024 Not Ready for Inspection JENNIFER RABUCHIN
Final 6/26/2024 Not Ready for Inspection JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/26/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 6/26/2024 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 6/26/2024 Not Ready for Inspection JENNIFER RABUCHIN
Verify Sprinkler Sign Off 6/26/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 8/12/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/12/2024 Corrections Issued JENNIFER RABUCHIN
Wood Frame 8/12/2024 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 8/23/2024 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 9/25/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 9/25/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 9/25/2024 Corrections Issued JENNIFER RABUCHIN
Insulation 9/27/2024 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 9/30/2024 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/10/2024 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 10/10/2024 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 10/10/2024 Approved JENNIFER RABUCHIN
Shower Pan 10/10/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/28/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/28/2025 Corrections Issued JENNIFER RABUCHIN
Final 1/28/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/28/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 1/28/2025 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 1/28/2025 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 1/28/2025 Approved JENNIFER RABUCHIN
Final 4/29/2025 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 4/29/2025 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 5/14/2025 Not Ready for Inspection JENNIFER RABUCHIN
Final 5/14/2025 Partial Inspection JENNIFER RABUCHIN
HVAC-Final 5/14/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/14/2025 Approved JENNIFER RABUCHIN
Service/Power Release 5/14/2025 Not Ready for Inspection JENNIFER RABUCHIN
Final 6/11/2025 OK to Issue CofO JENNIFER RABUCHIN
Service/Power Release 6/11/2025 Approved JENNIFER RABUCHIN