11612 W LA MAIDA ST 91601

Certificate Information: 11612 W LA MAIDA ST 91601

Application / Permit
23010-20000-03980
Plan Check / Job No.
B23VN13531
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 48' x 76'-1 13/16" IRR. SHAPED 2-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND OPEN TRELLIS; NFPA-13D THRU OUT
Permit Issued
Issued on 2/23/2024
Issuing Office
Valley
Current Status
CofO Issued on 11/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 SEAN SHAHMIRI
Corrections Issued 10/23/2023 SEAN SHAHMIRI
Quality Review Completed 10/27/2023 OMID HEDAYAT
Building Plans Picked Up 10/30/2023 APPLICANT
Applicant returned to address corrections 2/9/2024 SEAN SHAHMIRI
Plan Check Approved 2/9/2024 SEAN SHAHMIRI
Issued 2/23/2024 APPLICANT
CofO in Progress 11/12/2024 RAUL OLAGI
Permit Finaled 11/12/2024 DANIEL ORRANTE
CofO Issued 11/12/2024 DANIEL ORRANTE
Permit Finaled 11/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 11/13/2023 ASHLEY RODARTE
Address approval Cleared 11/14/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/15/2023 CARLOS AGUILERA
Sewer availability Cleared 11/15/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 11/17/2023 LAVEON RIDER
Specific Plan Cleared 1/22/2024 JOANNA MARROQUIN
Low Impact Development (LID) Cleared 2/5/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 2/5/2024 CARLOS AGUILERA
Trees in Parkway Cleared 2/6/2024 ADALBERTO VERA
Permit Cleared 2/12/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/28/2024 Corrections Issued MISAEL ESPARZA
Underground Mechanical 3/29/2024 Corrections Issued JUAN VALENZUELA
Special/Order Compliance 4/9/2024 Partial Inspection JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/17/2024 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/17/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 4/17/2024 Approved CHRISTOPHER ROJAS
Deputy Reinf. Concrete 4/18/2024 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 4/22/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 4/30/2024 Partial Approval JACK KARGODORIAN
Green Building Rough 4/30/2024 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 4/30/2024 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 4/30/2024 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 5/15/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/22/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 5/28/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 6/5/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/5/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 6/5/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 6/5/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/10/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/10/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 6/10/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 6/10/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 6/10/2024 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 6/10/2024 Approved CHRISTOPHER ROJAS
Wood Frame 6/10/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/17/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 6/17/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/17/2024 Approved CHRISTOPHER ROJAS
Shower Pan 6/17/2024 Approved CHRISTOPHER ROJAS
Wood Frame 6/17/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/21/2024 Approved CHRISTOPHER ROJAS
Insulation 6/21/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/21/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/26/2024 Partial Approval CHRISTOPHER ROJAS
Drywall Nailing 7/9/2024 Approved JENNIFER RABUCHIN
Pre-Inspection 8/30/2024 Partial Approval CHRISTOPHER ROJAS
Final 10/1/2024 Corrections Issued CHRISTOPHER ROJAS
Service/Power Release 10/1/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Special/Order Compliance 10/1/2024 Partial Approval CHRISTOPHER ROJAS
Final 10/8/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 10/8/2024 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 10/8/2024 Approved CHRISTOPHER ROJAS
Final 10/17/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Final 10/17/2024 Approved CHRISTOPHER ROJAS
Service/Power Release 10/17/2024 Approved CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 10/25/2024 Conditional Approval RAUL OLAGI
Deputy Reinf. Concrete 10/25/2024 Conditional Approval RAUL OLAGI
Final 10/25/2024 Corrections Issued CHRISTOPHER ROJAS
Final 11/12/2024 OK to Issue CofO RAUL OLAGI