7826 1/4-1/2 W KYLE ST 91040
Certificate Information: 7826 1/4-1/2 W KYLE ST 91040
- Application / Permit
- 23010-20000-03947
- Plan Check / Job No.
- B23VN12715
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW 21'2" X 36'5" TWO STORIES SFD UNIT PER SB9 TWO-UNIT DEVELOPMENT CA GOVT CODE 65852.21WITH ATTACHED ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(A) AT REAR OF THE LOT, NFPA-13D FIRE SPRINKLERS REQUIRED THOUGHOUT , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/17/2025
- Issuing Office
- Current Status
- CofO Issued on 6/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | RARES BODEA |
| Corrections Issued | 10/5/2023 | RARES BODEA |
| Quality Review Completed | 10/6/2023 | STEVEN KIM |
| Applicant returned to address corrections | 4/10/2024 | RARES BODEA |
| Applicant returned to address corrections | 8/14/2024 | RARES BODEA |
| Applicant returned to address corrections | 8/19/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 8/20/2024 | RARES BODEA |
| Applicant returned to address corrections | 12/16/2024 | RARES BODEA |
| Applicant returned to address corrections | 1/7/2025 | RARES BODEA |
| Plan Check Approved | 1/13/2025 | RARES BODEA |
| Issued | 1/17/2025 | APPLICANT |
| CofO in Progress | 4/14/2026 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 6/9/2026 | RUBEN SALAS |
| CofO Issued | 6/9/2026 | RUBEN SALAS |
| Permit Finaled | 6/9/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/13/2024 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 2/16/2024 | KURT CORRAL |
| Senate Bill 9 | Cleared | 3/19/2024 | BRENNEN OBETO |
| Low Impact Development (LID) | Cleared | 3/20/2024 | ERNEST TSE |
| GPI Written Notices | Cleared | 4/10/2024 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 4/10/2024 | RARES BODEA |
| Roof/Waste drainage to street | Cleared | 6/14/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 6/14/2024 | EDGAR ALCARAZ |
| Trees in Parkway | Cleared | 7/11/2024 | MIGUEL ORNELAS |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/3/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Samvelyan,, Taron; Lic. No.: C93740 | 1800 N VERDUGO RD APT 204 GLENDALE, CA 91208 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/20/2025 | Corrections Issued | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 3/7/2025 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 4/7/2025 | Partial Approval | WILLIAM WREN |
| Insulation | 4/7/2025 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 4/7/2025 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Partial Approval | WILLIAM WREN |
| Deputy Wood Construction | 6/6/2025 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2025 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 7/3/2025 | Conditional Approval | WILLIAM WREN |
| ELECTRICAL-Rough | 7/3/2025 | Approved | WILLIAM WREN |
| HVAC-Rough | 7/3/2025 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 7/3/2025 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 7/3/2025 | Approved | WILLIAM WREN |
| Shower Pan | 7/3/2025 | Approved | WILLIAM WREN |
| Insulation | 8/21/2025 | Not Ready for Inspection | WILLIAM WREN |
| Insulation | 8/25/2025 | Approved | WILLIAM WREN |
| Drywall Nailing | 9/4/2025 | Approved | WILLIAM WREN |
| Green Building Rough | 9/4/2025 | Approved | WILLIAM WREN |
| HVAC-Final | 2/23/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 2/23/2026 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 2/26/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 2/26/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 2/26/2026 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Final | 2/26/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 2/26/2026 | SGSOV Not Required | NICHOLAS TROWBRIDGE |
| Service/Power Release | 2/26/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 2/26/2026 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 2/26/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 4/10/2026 | OK to Issue CofO | NICHOLAS TROWBRIDGE |
| Green Building Final | 4/10/2026 | Approved | NICHOLAS TROWBRIDGE |
| Service/Power Release | 4/10/2026 | Approved | NICHOLAS TROWBRIDGE |