12237-12239 W HUSTON ST 91607
Certificate Information: 12237-12239 W HUSTON ST 91607
- Application / Permit
- 23010-20000-03927
- Plan Check / Job No.
- B23VN13343
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 66'-8" X 49'-6" 2 STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE, PATIO COVER AND ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
- Permit Issued
- Issued on 2/20/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2023 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 10/17/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 10/19/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 10/25/2023 | APPLICANT |
| Applicant returned to address corrections | 12/26/2023 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 2/15/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 2/20/2024 | APPLICANT |
| CofO in Progress | 1/3/2025 | OGANES TARAKHCHYAN |
| CofO in Progress | 1/10/2025 | RAUL OLAGI |
| CofO in Progress | 1/28/2025 | RAUL OLAGI |
| CofO in Progress | 1/28/2025 | RAUL OLAGI |
| CofO in Progress | 1/28/2025 | RAUL OLAGI |
| Permit Finaled | 2/4/2025 | RUBEN SALAS |
| CofO Issued | 2/4/2025 | RUBEN SALAS |
| Permit Finaled | 2/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Hold | Cleared | 11/6/2023 | MARIA VENDIVIL |
| Miscellaneous | Cleared | 11/6/2023 | JOANNA MARROQUIN |
| Address approval | Cleared | 11/7/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2023 | EDGAR ALCARAZ |
| Permit | Cleared | 11/7/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 11/7/2023 | EDGAR ALCARAZ |
| Miscellaneous | Cleared | 11/29/2023 | STEVEN WECHSLER |
| Low Impact Development (LID) | Cleared | 12/8/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 12/8/2023 | EDGAR ALCARAZ |
| Trees in Parkway | Cleared | 12/11/2023 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 12/18/2023 | LAVEON RIDER |
| Specific Plan | Cleared | 2/15/2024 | JOANNA MARROQUIN |
| ZI | Cleared | 2/15/2024 | JOANNA MARROQUIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/20/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Deputy Reinf. Concrete | 4/4/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 4/4/2024 | Partial Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 4/8/2024 | Corrections Issued | JOSE AVILA |
| Deputy Reinf. Concrete | 4/10/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/18/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 4/19/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 4/19/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 4/19/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 4/19/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 5/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Structural Steel Frame | 5/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 5/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 5/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 5/15/2024 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 5/15/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 5/17/2024 | Corrections Issued | JOHN COLEMAN |
| Green Building Rough | 5/17/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Structural Steel Frame | 5/17/2024 | Corrections Issued | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 5/17/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Wood Frame | 5/17/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Shower Pan | 6/4/2024 | Approved | SALVADOR MARTINEZ |
| Deputy Wood Construction | 6/13/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2024 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 6/13/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/26/2024 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 7/5/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/10/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 7/10/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/11/2024 | Approved | SALVADOR MARTINEZ |
| Insulation | 7/17/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Insulation | 7/19/2024 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 7/29/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/23/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 12/27/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Service/Power Release | 12/27/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/3/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 1/3/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 1/3/2025 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 1/3/2025 | SGSOV Not Required | OGANES TARAKHCHYAN |
| Smoke Detectors | 1/3/2025 | Approved | OGANES TARAKHCHYAN |