11729 N PRIMROSE CT 91326

Certificate Information: 11729 N PRIMROSE CT 91326

Application / Permit
23010-20000-03926
Plan Check / Job No.
B23VN13335
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
eplan. NEW ACCESSORY STRUCTURE (OUTDOOR COVERED PATIO AND BATHROOM).
Permit Issued
Issued on 12/27/2024
Issuing Office
Current Status
CofO Issued on 8/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2023 APPLICANT
Assigned to Plan Check Engineer 10/18/2023 KAVIAN REFAHI
Corrections Issued 10/31/2023 KAVIAN REFAHI
Quality Review Completed 11/8/2023 REZA HAGHIGHAT
Applicant returned to address corrections 3/19/2024 KAVIAN REFAHI
Applicant returned to address corrections 7/30/2024 KAVIAN REFAHI
Applicant returned to address corrections 9/23/2024 KAVIAN REFAHI
Applicant returned to address corrections 10/10/2024 KAVIAN REFAHI
Applicant returned to address corrections 10/17/2024 KAVIAN REFAHI
Applicant returned to address corrections 10/25/2024 KAVIAN REFAHI
Applicant returned to address corrections 11/13/2024 KAVIAN REFAHI
Applicant returned to address corrections 11/27/2024 KAVIAN REFAHI
Plan Check Approved 12/26/2024 KAVIAN REFAHI
Issued 12/27/2024 APPLICANT
CofO in Progress 7/22/2025 JEFFREY PARD
Permit Finaled 8/20/2025 JOHN JANSON
CofO Issued 8/20/2025 JOHN JANSON
Permit Finaled 8/20/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/30/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 9/30/2024 RYAN CASTRO
"T" removal Cleared 10/10/2024 JAZMIN ROQUE
CPC Cleared 10/10/2024 JAZMIN ROQUE
Tract Map conditions Cleared 10/10/2024 JAZMIN ROQUE
ZA Case Cleared 10/10/2024 JAZMIN ROQUE
ZA Case Cleared 10/10/2024 JAZMIN ROQUE
ZA Case Cleared 10/10/2024 JAZMIN ROQUE
ZA Case Cleared 10/10/2024 JAZMIN ROQUE
GPI Written Notices Cleared 10/24/2024 KAVIAN REFAHI
Grading Pre-Inspection Cleared 10/24/2024 KAVIAN REFAHI
Distance to fire station Cleared 12/18/2024 JERRY KAO
Hydrant and Access approval Cleared 12/18/2024 JERRY KAO

Contact Information

Contractor L A Construction Group Inc; Lic. No.: 873259-B       ,
Contractor L A Hardwood Floors & Remodeling Inc; Lic. No.: 873259-B       ,
Engineer Miller,, Karen Lynn; Lic. No.: GE2257 6634 VALJEAN AVENUE      VAN NUYS, CA 91406
Engineer Mniarji,, Majd Sameer; Lic. No.: NA93049       ,
Geologist Putnam,, Lance Richard; Lic. No.: EG2469 6634 VALJEAN AVE      VAN NUYS, CA 91406

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/11/2025 Partial Approval JEFFREY PARD
Sewer 2/11/2025 Approved JEFFREY PARD
Excavation/Setback/Form/Re-Bar 2/28/2025 Approved JEFFREY PARD
PLUMBING-Rough 2/28/2025 Partial Approval JEFFREY PARD
Piling/Pier/Caisson 2/28/2025 Approved JEFFREY PARD
Deputy Reinf. Concrete 3/3/2025 Conditional Approval STEVEN BACK
Footing/Foundation/Slab 3/3/2025 Approved JEFFREY PARD
BUILDING-Rough-Frame 4/3/2025 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 4/3/2025 Not Ready for Inspection JEFFREY PARD
Green Building Rough 4/3/2025 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 4/3/2025 Approved JEFFREY PARD
Verify Sprinkler Sign Off 4/3/2025 Corrections Issued JEFFREY PARD
ELECTRICAL-Rough 4/7/2025 Approved JEFFREY PARD
BUILDING-Rough-Frame 4/24/2025 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Not Ready for Inspection JEFFREY PARD
Green Building Rough 4/24/2025 Not Ready for Inspection JEFFREY PARD
Insulation 4/24/2025 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 4/24/2025 Partial Approval JEFFREY PARD
Verify Sprinkler Sign Off 4/24/2025 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 5/9/2025 Approved JEFFREY PARD
Green Building Rough 5/9/2025 Approved JEFFREY PARD
Insulation 5/9/2025 Approved JEFFREY PARD
Verify Sprinkler Sign Off 5/9/2025 Approved JEFFREY PARD
Interior/Exterior Lathing 5/14/2025 Approved SCOTT SOBEL
ELECTRICAL-Rough 6/12/2025 Approved JEFFREY PARD
Final 6/20/2025 OK to Issue CofO JEFFREY PARD
Green Building Final 6/20/2025 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 6/20/2025 SGSOV Approved JEFFREY PARD
Service/Power Release 6/20/2025 Approved JEFFREY PARD
Smoke Detectors 6/20/2025 Approved JEFFREY PARD