9379 N ILEX AVE 91352

Certificate Information: 9379 N ILEX AVE 91352

Application / Permit
23010-20000-03899
Plan Check / Job No.
B23VN13241
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan New 44' 8" x 28' 3" ADU per LAMC 12.22 A.33 (c)-(d) with attached patio cover. All work done per engineer.
Permit Issued
Issued on 7/31/2024
Issuing Office
Current Status
CofO Issued on 10/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 NAREG ATARIAN
Corrections Issued 10/13/2023 NAREG ATARIAN
Quality Review Completed 10/19/2023 OMID HEDAYAT
Applicant returned to address corrections 2/29/2024 NAREG ATARIAN
Plan Check Approved 7/29/2024 NAREG ATARIAN
Issued 7/31/2024 APPLICANT
CofO in Progress 10/6/2025 VINCENT HANLEY
Permit Finaled 10/28/2025 RUBEN SALAS
CofO Issued 10/28/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/18/2023 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 10/19/2023 MARKOS PEREZ-BRAN
ZA Case Cleared 1/26/2024 RYAN LY
Low Impact Development (LID) Cleared 2/14/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 2/21/2024 JOHN LIN
Private sewage disp. approval Cleared 7/11/2024 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/25/2025 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 2/28/2025 Approved MATTHEW NELSON
Deputy Drilled-In Anchors 4/1/2025 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/17/2025 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Rough 4/17/2025 Corrections Issued DAVID MATSON
Green Building Rough 4/17/2025 Approved DAVID MATSON
HVAC-Rough 4/17/2025 Corrections Issued DAVID MATSON
Interior/Exterior Lathing 4/17/2025 Partial Approval DAVID MATSON
PLUMBING-Rough 4/17/2025 Corrections Issued DAVID MATSON
Verify Sprinkler Sign Off 4/17/2025 Partial Inspection DAVID MATSON
ELECTRICAL-Rough 4/21/2025 Approved WILLIAM WREN
HVAC-Rough 4/21/2025 Approved WILLIAM WREN
PLUMBING-Rough 4/21/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 4/22/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 4/22/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 4/30/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 5/2/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 5/2/2025 Not Ready for Inspection MICHAEL CORTEZ
Shower Pan 5/2/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 5/7/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 7/10/2025 Not Ready for Inspection DAVID MATSON
Final 7/10/2025 Not Ready for Inspection DAVID MATSON
Green Building Final 7/10/2025 Not Ready for Inspection DAVID MATSON
SGSOV-Seismic Gas S/O Valve 7/10/2025 SGSOV Not Ready DAVID MATSON
Service/Power Release 7/10/2025 Not Ready for Inspection DAVID MATSON
Smoke Detectors 7/10/2025 Not Ready for Inspection DAVID MATSON
Verify Sprinkler Sign Off 7/10/2025 Not Ready for Inspection DAVID MATSON
BUILDING-Rough-Frame 7/23/2025 Partial Approval VINCENT HANLEY
Final 7/23/2025 Corrections Issued VINCENT HANLEY
Green Building Final 7/23/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/23/2025 SGSOV Not Required VINCENT HANLEY
Service/Power Release 7/23/2025 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 7/23/2025 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 7/23/2025 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 8/7/2025 Partial Approval MATTHEW NELSON
Final 8/7/2025 Corrections Issued MATTHEW NELSON
Service/Power Release 8/7/2025 Corrections Issued MATTHEW NELSON
Verify Sprinkler Sign Off 8/7/2025 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 10/3/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 10/3/2025 Approved VINCENT HANLEY
Final 10/3/2025 OK to Issue CofO VINCENT HANLEY
HVAC-Final 10/3/2025 Approved VINCENT HANLEY
PLUMBING-Final 10/3/2025 Approved VINCENT HANLEY
Service/Power Release 10/3/2025 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 10/3/2025 Not Ready for Inspection VINCENT HANLEY