10046-10048 N PALI AVE 91042
Certificate Information: 10046-10048 N PALI AVE 91042
- Application / Permit
- 23010-20000-03872
- Plan Check / Job No.
- B23VN13102
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 20'3" X 20'8" ATTACHED GARAGE AND (N) 22'9" X 23'8" IRREGULARLY SHAPED ADDITION (120 SF) TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (e). WORK TO BE DONE PER ARCHITECT DESIGN.
- Permit Issued
- Issued on 10/19/2023
- Issuing Office
- Current Status
- CofO Issued on 5/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2023 | MADISON ODELL |
| Corrections Issued | 9/30/2023 | MADISON ODELL |
| Applicant returned to address corrections | 10/11/2023 | MADISON ODELL |
| Plan Check Approved | 10/16/2023 | MADISON ODELL |
| Issued | 10/19/2023 | APPLICANT |
| CofO in Progress | 5/13/2024 | WILLIAM WREN |
| Permit Finaled | 5/15/2024 | RUBEN SALAS |
| CofO Issued | 5/15/2024 | RUBEN SALAS |
| Permit Finaled | 5/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/6/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2023 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 10/6/2023 | MANUEL TEJADA |
| Roof/Waste drainage to street | Cleared | 10/6/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 10/10/2023 | COLIN LOREDO |
| GPI Written Notices | Cleared | 10/11/2023 | MADISON ODELL |
Contact Information
| Architect | Menachekanian,, Asik A; Lic. No.: NA28213 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/14/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 12/19/2023 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 12/19/2023 | Partial Approval | WILLIAM WREN |
| Sewer | 12/19/2023 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 12/20/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 2/6/2024 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 2/6/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2024 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 2/6/2024 | Approved | WILLIAM WREN |
| Wood Frame | 2/6/2024 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Partial Approval | WILLIAM WREN |
| Insulation | 2/14/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 2/14/2024 | Partial Approval | WILLIAM WREN |
| Drywall Nailing | 2/20/2024 | Approved | WILLIAM WREN |
| Gas Test | 2/20/2024 | Approved | WILLIAM WREN |
| Shower Pan | 2/20/2024 | Approved | WILLIAM WREN |
| HVAC-Rough | 2/27/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 2/27/2024 | Approved | WILLIAM WREN |
| Final | 4/15/2024 | Corrections Issued | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 4/15/2024 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 4/15/2024 | Approved | WILLIAM WREN |
| Final | 4/18/2024 | OK to Issue CofO | WILLIAM WREN |