7761 N AURA AVE 91335
Certificate Information: 7761 N AURA AVE 91335
- Application / Permit
- 23010-20000-03825
- Plan Check / Job No.
- B23VN12917
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 29' X 31' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 4/10/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/6/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2023 | SERGIO MUNIZ |
| Corrections Issued | 9/28/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 10/3/2023 | APPLICANT |
| Plan Check Approved | 3/1/2024 | ISIS ARGUETA |
| Issued | 4/10/2024 | APPLICANT |
| CofO in Progress | 12/31/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 1/6/2026 | JOHN JANSON |
| CofO Issued | 1/6/2026 | JOHN JANSON |
| Permit Finaled | 1/6/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/6/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 10/10/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 1/18/2024 | OSCAR CASTRO |
| Low Impact Development (LID) | Cleared | 2/23/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 2/26/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 5/15/2024 | Not Ready for Inspection | JEFFREY BULL |
| Special/Order Compliance | 5/15/2024 | Corrections Issued | JEFFREY BULL |
| Underground Mechanical | 5/15/2024 | Approved | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 6/14/2024 | Partial Approval | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 6/18/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 7/22/2024 | Not Ready for Inspection | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 7/22/2024 | Not Ready for Inspection | JEFFREY BULL |
| Verify Sprinkler Sign Off | 7/22/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 8/7/2024 | Approved | JEFFREY PARD |
| Rough-Elec/Plmb/HVAC | 8/7/2024 | Approved | JEFFREY BULL |
| Sewer | 8/7/2024 | Approved | JEFFREY PARD |
| Insulation | 8/15/2024 | Corrections Issued | JEFFREY BULL |
| Interior/Exterior Lathing | 8/15/2024 | Not Ready for Inspection | JEFFREY BULL |
| Drywall Nailing | 8/20/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 8/20/2024 | Approved | JEFFREY BULL |
| Special/Order Compliance | 9/23/2024 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 8/12/2025 | Approved | ARUTYUN MADATYAN |
| Final | 8/12/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 8/12/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Final | 8/12/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Rough | 8/12/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 8/12/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 8/12/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 8/12/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 10/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 10/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 10/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 10/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 10/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 10/21/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 10/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 11/25/2025 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 11/25/2025 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 11/25/2025 | SGSOV Not Required | ROBERT GOLD |
| Service/Power Release | 11/25/2025 | Not Ready for Inspection | ROBERT GOLD |
| Final | 12/2/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Grounding or Bonding | 12/2/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 12/2/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 12/30/2025 | Approved | ARUTYUN MADATYAN |
| Final | 12/30/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 12/30/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 12/30/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 12/30/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 1/6/2026 | Approved | ARUTYUN MADATYAN |