14216 W LEMAY ST 91405
Certificate Information: 14216 W LEMAY ST 91405
- Application / Permit
- 23010-20000-03787
- Plan Check / Job No.
- B23VN12779
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ONE-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) WITH ATTACHED PATIO COVER. WORK PER ENGINEER.
- Permit Issued
- Issued on 5/16/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2023 | JESSE ARELLANO |
| Corrections Issued | 9/26/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 9/28/2023 | APPLICANT |
| Applicant returned to address corrections | 11/28/2023 | ROSENDO MEDINA |
| Plan Check Approved | 11/29/2023 | ISIS ARGUETA |
| Issued | 5/16/2024 | APPLICANT |
| CofO in Progress | 7/7/2025 | RYAN SALAZAR |
| Permit Finaled | 7/10/2025 | RUBEN SALAS |
| Permit Finaled | 7/10/2025 | RUBEN SALAS |
| CofO Issued | 7/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/4/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 10/16/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 10/30/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 11/1/2023 | NIKKI ZULUETA |
| Hydrant and Access approval | Cleared | 11/15/2023 | LAVEON RIDER |
| HPOZ | Cleared | 11/20/2023 | ERIK VAN BREENE |
Contact Information
| Contractor | Dominguez Construction; Lic. No.: 898182-B | 10681 ILEX AVE PACOIMA, CA 91331 |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 14537 VENTURA BLVD SHERMAN OAKS, CA 91403 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/20/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/20/2024 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/3/2024 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 6/6/2024 | Approved | RYAN SALAZAR |
| Deputy Wood Construction | 7/2/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 7/3/2024 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 7/3/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Wood Frame | 7/3/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 7/10/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 7/10/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Shower Pan | 7/10/2024 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 7/12/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 7/12/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 7/12/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/12/2024 | Partial Approval | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 7/12/2024 | Approved | RYAN SALAZAR |
| Insulation | 7/18/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/18/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 7/22/2024 | Approved | RYAN SALAZAR |
| Sewer | 8/9/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 8/9/2024 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 8/12/2024 | Approved | RYAN SALAZAR |
| Final | 4/25/2025 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 4/25/2025 | Approved | RYAN SALAZAR |
| Green Building Final | 4/25/2025 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 4/25/2025 | SGSOV Not Required | RYAN SALAZAR |
| Service/Power Release | 4/25/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 4/25/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 6/3/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/3/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 6/11/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 6/11/2025 | Approved | RYAN SALAZAR |
| Service/Power Release | 6/11/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 7/3/2025 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 7/3/2025 | Approved | RYAN SALAZAR |