14216 W LEMAY ST 91405

Certificate Information: 14216 W LEMAY ST 91405

Application / Permit
23010-20000-03787
Plan Check / Job No.
B23VN12779
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ONE-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) WITH ATTACHED PATIO COVER. WORK PER ENGINEER.
Permit Issued
Issued on 5/16/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2023 APPLICANT
Assigned to Plan Check Engineer 9/26/2023 JESSE ARELLANO
Corrections Issued 9/26/2023 JESSE ARELLANO
Building Plans Picked Up 9/28/2023 APPLICANT
Applicant returned to address corrections 11/28/2023 ROSENDO MEDINA
Plan Check Approved 11/29/2023 ISIS ARGUETA
Issued 5/16/2024 APPLICANT
CofO in Progress 7/7/2025 RYAN SALAZAR
Permit Finaled 7/10/2025 RUBEN SALAS
Permit Finaled 7/10/2025 RUBEN SALAS
CofO Issued 7/10/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/4/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 10/16/2023 NIKKI ZULUETA
Sewer availability Cleared 10/16/2023 NIKKI ZULUETA
Low Impact Development (LID) Cleared 10/30/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 11/1/2023 NIKKI ZULUETA
Hydrant and Access approval Cleared 11/15/2023 LAVEON RIDER
HPOZ Cleared 11/20/2023 ERIK VAN BREENE

Contact Information

Contractor Dominguez Construction; Lic. No.: 898182-B 10681 ILEX AVE      PACOIMA, CA 91331
Engineer Valencia,, Byron Steve; Lic. No.: C87372 14537 VENTURA BLVD      SHERMAN OAKS, CA 91403

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/20/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 5/20/2024 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/3/2024 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 6/6/2024 Approved RYAN SALAZAR
Deputy Wood Construction 7/2/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 7/3/2024 Partial Approval RYAN SALAZAR
Shower Pan 7/3/2024 Not Ready for Inspection RYAN SALAZAR
Wood Frame 7/3/2024 Approved RYAN SALAZAR
HVAC-Rough 7/10/2024 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 7/10/2024 Corrections Issued SALVADOR MARTINEZ
Shower Pan 7/10/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/12/2024 Approved RYAN SALAZAR
Green Building Rough 7/12/2024 Approved RYAN SALAZAR
HVAC-Rough 7/12/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/12/2024 Partial Approval RYAN SALAZAR
Verify Sprinkler Sign Off 7/12/2024 Approved RYAN SALAZAR
Insulation 7/18/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/18/2024 Approved RYAN SALAZAR
Drywall Nailing 7/22/2024 Approved RYAN SALAZAR
Sewer 8/9/2024 Approved RYAN SALAZAR
Underground Mechanical 8/9/2024 Partial Approval RYAN SALAZAR
Underground Mechanical 8/12/2024 Approved RYAN SALAZAR
Final 4/25/2025 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 4/25/2025 Approved RYAN SALAZAR
Green Building Final 4/25/2025 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/25/2025 SGSOV Not Required RYAN SALAZAR
Service/Power Release 4/25/2025 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 4/25/2025 Approved RYAN SALAZAR
Drywall Nailing 6/3/2025 Not Ready for Inspection RYAN SALAZAR
Interior/Exterior Lathing 6/3/2025 Not Ready for Inspection RYAN SALAZAR
Final 6/11/2025 Not Ready for Inspection RYAN SALAZAR
Green Building Final 6/11/2025 Approved RYAN SALAZAR
Service/Power Release 6/11/2025 Not Ready for Inspection RYAN SALAZAR
Final 7/3/2025 OK to Issue CofO RYAN SALAZAR
Service/Power Release 7/3/2025 Approved RYAN SALAZAR