7828 W KYLE ST 91040
Certificate Information: 7828 W KYLE ST 91040
- Application / Permit
- 23010-20000-03755
- Plan Check / Job No.
- B23VN12713
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN NEW 20' X 54'-5" IRREGULAR SHAPED 2-STORY SFD W/ 2-CAR GARAGE per SB9 Two-Unit Development Ca Govt Code 65852.21. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/16/2024
- Issuing Office
- Current Status
- CofO in Progress on 4/14/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | RAPHAEL ROSAS |
| Corrections Issued | 10/3/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 10/6/2023 | STEVEN KIM |
| Applicant returned to address corrections | 4/1/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/26/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 8/29/2024 | RAPHAEL ROSAS |
| Issued | 9/16/2024 | APPLICANT |
| CofO in Progress | 4/14/2026 | NICHOLAS TROWBRIDGE |
Permit Application Clearance Information
| Address approval | Cleared | 11/6/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2023 | NIKKI ZULUETA |
| Hydrant and Access approval | Cleared | 2/16/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 3/20/2024 | ERNEST TSE |
| Senate Bill 9 | Cleared | 5/8/2024 | JASON CHAN |
| Miscellaneous | Cleared | 5/28/2024 | GREGORIO GUILLERMO |
| Permit | Cleared | 6/14/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 6/14/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 6/14/2024 | EDGAR ALCARAZ |
| GPI Written Notices | Cleared | 8/29/2024 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 8/29/2024 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Samvelyan,, Taron; Lic. No.: C93740 | 1800 N VERDUGO RD APT 204 GLENDALE, CA 91208 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/30/2024 | Partial Inspection | WILLIAM WREN |
| Pre-Inspection | 2/24/2025 | Partial Inspection | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 3/7/2025 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 4/7/2025 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 4/7/2025 | Approved | WILLIAM WREN |
| Insulation | 4/7/2025 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 4/7/2025 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Partial Approval | WILLIAM WREN |
| Deputy Wood Construction | 6/6/2025 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2025 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 7/3/2025 | Conditional Approval | WILLIAM WREN |
| HVAC-Rough | 7/3/2025 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 7/3/2025 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 7/3/2025 | Approved | WILLIAM WREN |
| Shower Pan | 7/3/2025 | Approved | WILLIAM WREN |
| Insulation | 8/25/2025 | Approved | WILLIAM WREN |
| Drywall Nailing | 9/4/2025 | Approved | WILLIAM WREN |
| Green Building Rough | 9/4/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 2/27/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 2/27/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 2/27/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 2/27/2026 | SGSOV Not Required | NICHOLAS TROWBRIDGE |
| Service/Power Release | 2/27/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 2/27/2026 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 2/27/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 4/10/2026 | OK to Issue CofO | NICHOLAS TROWBRIDGE |
| Green Building Final | 4/10/2026 | Approved | NICHOLAS TROWBRIDGE |